The following data relate to direct labor costs for the current period: Standard costs 5,000...

Question:

The following data relate to direct labor costs for the current period:

Standard costs 5,000 hours at $11.00
Actual Costs 6,500 hours at $10.60

What is the direct labor rate variance?

Variances:

When the actual costs differ from the standard costs then variance calculations are often performed. Some examples are the direct labor rate variance and the direct material price variance.

Answer and Explanation: 1

Become a Study.com member to unlock this answer!

View this answer

Answer: $2,600

Explanation:

This is calculated as:

{eq}\begin{align} \text{Direct labor rate variance} &= (\text{Standard rate} - \text{Actual...

See full answer below.


Learn more about this topic:

Loading...
Budget Variance Definition, Analysis & Calculation

from

Chapter 9 / Lesson 16
3.9K

Learn about budget variance. Understand what budget variance is, identify what constitutes positive budget variance, and learn how to calculate budget variance.


Related to this Question

Explore our homework questions and answers library