The difference between the actual cost and the standard cost for direct labor is called: A....
Question:
The difference between the actual cost and the standard cost for direct labor is called:
A. Direct Labor Rate Variance
B. Direct Labor Efficiency Variance
C. Direct Labor Split Variance
D. Direct Labor Flexible Budget Variance
E. None of the above
Variances:
Variance is computed to show the deviation of actual data from the standard data. Variances may be positive or negative. The positive variance shows favorable conditions, and the negative variance shows unfavorable conditions.
Answer and Explanation: 1
Become a Study.com member to unlock this answer! Create your account
View this answerCorrect option: Option A
Explanation:
Direct labor rate variation means the difference between the standard direct labor cost and the actual direct...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:
from
Chapter 11 / Lesson 3Learn how to calculate variances with direct materials and direct labor. Variances are changes to the costs an organization has budgeted, they can be either favorable or unfavorable.
Related to this Question
- A performance report for direct labor shows a variance between the budget and actual amounts. This difference is a: A. budget variance B. direct labor efficiency variance C. direct labor spending variance D. direct labor rate variance
- Standard and actual costs for direct labor for the manufacture of 1,000 units of product were as follows: Actual costs 960 hours @ $36.00 Standard costs 970 hours@ 35.50 Determine: A. variance B. rate variance C. total direct labor cost variance
- The formula AH * (SR - AR) is the: a. direct labor spending variance. b. direct labor volume variance. c. direct labor rate variance. d. direct labor efficiency variance.
- The difference between standard and actual cost per unit of input is measured by: a. the raw materials price variance. b. the direct labor rate variance. c. the variable overhead spending variance. d. all of the above
- The variance that is least related to cost control is: A. flexible-budget variance. B. direct materials price variance. C. direct labor rate (price) variance. D. production volume variance.
- The standard rate of pay is $12 per direct labor hour. If the actual direct labor payroll was $51,744 for 4,400 direct labor hours worked, the direct labor price (rate) variance is (blank).
- The total direct labour hour variance for Curb Corp is $7,500 F. The direct labour efficiency variance is $2,700 U. If the total direct labour cost is $25,000 and the actual direct labour rate is $40, what is the standard rate?
- Actual total direct labor 546,000 Actual hours worked 26,000 Standard labor-hours allowed for actual output (flexible budget) 27,000 Direct labor price variance 19,500 u Actual variable overhead 132,600 Standard variable overhead rate per standard dir
- Standard and actual costs for direct labor for the manufacture of 1,500 units of product were as follows: Determine the (a) time variance, (b) rate variance, and (c) total direct labor cost variance.
- The standard rate of pay is $10 per direct labor hour. If the actual direct labor payroll was $39,200 for 4,000 direct labor hours worked, the direct labor price (rate) variance is: a. $1,000 U. b. $800 F. c. $1,000 F. d. $800 U.
- Standard and actual costs for direct labor for the manufacture of 300 units of product were as follows: Actual costs 125 hours @ $54.00; Standard costs 131 hours @ $53.00. Determine the direct labor (a) time variance, (b) rate variance.
- The standard rate of pay is $5 per direct labor hour. If the actual direct labor payroll was $19,600 for 4,000 direct labor hours worked, the direct labor price (rate) variance is __________.
- The standard rate of pay is $20 per direct labor hour. If the actual direct labor payout was $121,520 for 6,200 direct labor hours worked, the direct labor price (rate) variance is: a. $3,100 favorabl
- How is the direct labor rate variance calculated? A. The difference between the standard labor rate and the actual labor rate B. The difference between the standard labor rate and the actual labor rate multiplied by the actual labor hours used C. The diff
- Calculate variable overhead spending variance if actual labor hours used are 260, the standard variable overhead rate is $10.40 per direct labor hour and actual variable overhead rate is $9.30 per direct labor hour. Also, specify whether the variance is f
- A fixed overhead volume variance based on standard direct labor hours measures A. deviation from standard direct labor hour capacity. B. deviation from the denominator level of direct labor hours. C. fixed overhead efficiency. D. fixed overhead spending.
- The standard costs and actual costs for direct labor for the manufacture of 2,500 actual units of product are as follows. Standard costs: 7,500 hours at $12 Actual costs: 7,400 hours at $11.40 The amount of the direct labor rate variance is: a. $4,440 fav
- The total manufacturing cost variance consists of: a. direct materials cost variance, direct labor rate variance, and factory overhead cost variance b. direct materials price variance, direct labor cost variance, and fixed factory overhead volume variance
- The standard costs and actual costs for direct labor for the manufacture of 2,500 units of product are as follows. Standard costs: 7,500 hours at $12.00 Actual costs: 7,400 hours at $11.40 The amount of the direct labor efficiency variance is: a. $1,140 f
- The per-unit standards for direct labor are 1.5 direct labor hours at $12 per hour. If in producing 2,400 units, the actual direct labor cost was $36,800 for 3,000 direct labor hours worked, what is the total direct labor variance? a. $1,920 U b. $6,400 F
- The flexible-budget variance for materials is $7,000 (U). The sales-volume variance is $17,000 (U). The price variance for material is $36,000 (F). The efficiency variance for direct manufacturing labor is $10,000 (F). Calculate the efficiency variance fo
- Carpe Diem Co. reported the following variances for the period: Direct materials price variance: $1,700 U Direct labor efficiency variance: 23,600 U Fixed overhead volume variance: 10,200 U Fixed overhead budget variance: 20,000 F Direct materials qu
- If the actual direct labor hours spent producing a commodity differ from the standard hours, the variance is termed: a. time variance b. price variance c. quantity variance d. rate variance
- The standard costs and actual costs for direct labor for the manufacture of 2,500 units of product are as follows. Standard cost of direct labor = 7,500 hours at $12.00 Actual cost of direct labor = 7,400 hours at $11.40 What is the amount of the direct l
- Which variance is directly impacted if the employees who build the product go on strike and temporary workers who are slower and not as skilled are hired? A. Direct labor efficiency variance B. Direct materials price variance C. Direct labor rate varianc
- How is the direct labor rate variance calculated? A. The difference between the standard labor rate and the actual labor rate multiplied by the actual labor hours used. B. The difference between the standard labor rate and the actual labor rate. C. The di
- The difference between the split cost and the actual cost for direct materials is called the: A. Materials Price Variance B. Materials Efficiency Variance C. Materials Usage Variance D. Materials Budget Variance E. None of the above
- A favorable materials price variance can affect all of the following variances except A) labor rate variance B) labor efficiency variance C) materials quantity variance D) flexible budget variance for direct materials
- "The difference between actual hours worked and standard hours allowed for the good units produced, multiplied by the standard labor rate" is a description of the: a. direct labor rate variance. b. direct labor efficiency variance. c. total direct labo
- Variable overhead is applied on the basis of standard direct labor hours. If the direct labor efficiency variance is unfavorable, the variable overhead efficiency variance will be: A. favorable. B. unfavorable. C. zero. D. indeterminable since it is not r
- The cost of available but unused productive capacity is indicated by the: a. direct labor cost rate variance. b. direct labor cost time variance. c. fixed factory overhead volume variance. d. variable factory overhead controllable variance.
- The following data relate to direct labor costs for the current period: Standard costs 5,000 hours at $11.00 Actual Costs 6,500 hours at $10.60 What is the direct labor rate variance?
- A five-percent wage increase for all factory employees would affect which of the following variances? a. direct materials price variance b. variable manufacturing overhead efficiency variance c. direct labor rate variance d. direct labor efficiency va
- The standard costs and actual costs for direct labor for the manufacture of 2,500 actual units of product are as follows: Standard Costs Direct labor 7,500 hours $12.00 Actual Costs Direct labor 7,40
- Consider the following information: Actual direct labor hours 34,500 Standard direct labor hours 35,000 Total actual direct labor cost $241,500 Direct-labor efficiency variance $3,200F The direct-labor rate variance is: A. $17,250U. B. $20,700U. C. $2
- The direct labor time variance is the difference between the a) actual labor rate and the standard labor rate b) actual hours at the standard rate and the standard costs c) actual costs and the actual hours at the standard rate d) actual costs and sta
- The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 3,500 units, the actual direct labor cost was $69,750 for 4,500 direct labor hours worked, the total direct labor variance is?
- The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,200 units, the actual direct labor cost was $32,000 for 2,000 direct labor hours worked, the total direct labor variance is __________.
- Standard and actual costs for direct labor for the manufacture of 1,500 units of product were as follows: Actual costs 450 hours at $17.00, Standard costs 455 hours at $16.50. Determine the (i) time variance, (ii) rate variance, and (iii) total direct lab
- Bok Company's output for the current period was assigned a $419,000 standard direct labor cost. The direct labor variances included a $10,475 unfavorable direct labor rate variance and a $4,190 favorable direct labor efficiency variance. What is the actua
- Question 35 The standard rate of pay is $12 per direct labor hour. If the actual direct labor payroll was $47,040 for 4,000 direct labor hours worked, the direct labor price (rate) variance is a. $960
- Prime cost is: a. direct labor cost and indirect labor cost. b. indirect materials cost and direct labor cost. c. direct materials cost and direct labor cost. d. direct materials cost and direct labor cost.
- The following data relate to direct labor costs for the current period: Standard costs 6,000 hours at $12.00 Actual costs 7,500 hours at $11.60 What is the direct labor rate variance? A.$15,000
- The following data relate to direct labor costs for the current period: Standard costs 9,000 hours at $5.50 Actual costs 8,500 hours at $5.75 What is the direct labor rate variance?
- The standard direct labor cost per unit for a company was $13.50 ($27 per hour x 0.5 hours per unit). During the period, actual direct labor costs amounted to $89,000, 3,200 labor hours were worked, and 5,200 units were produced. Compute the direct labor
- The standard costs and actual costs for direct labor for the manufacture of 2,500 actual units of product are as follows: Standard Costs Direct Labor 7,500 hours @ $11.80 Actual Costs Direct Labor 7,
- The standard rate of pay is $20 per direct labor hour. If the actual direct labor payroll was $117,600 for 6,000 direct labor hours worked, the direct labor price (rate) variance is: a. $2,400 unfavorable. b. $2,400 favorable. c. $3,000 unfavorable. d. $3
- Direct Labor rate variance is the difference between a.(Actual hours used) * (actual rate - standard rate) b.(Actual hours used) * (actual rate + standard rate) c.(Actual hours used) * (standard rate - actual rate) d.(Actual hours used - standard hour
- The standard cost of direct labor per hour is $12.50. One and one half standard direct labor hours are allowed per unit of finished goods. During the current period, 560 units were produced using 1,259 direct labor hours. The direct labor rate variance is
- Consider the following information: Actual direct labor hours 34,500 Standard direct labor hours 35,000 Total actual direct labor cost $241,500 Direct-labor efficiency variance, favorable $3,200 The direct-labor rate variance is: - $17,250U. - $20
- The standard rate of pay is $12 per direct labor hour. If the actual direct labor payroll was $51744 for 4400 direct labor hours worked, the direct labor price (rate) variance is: a. $1200 unfavorable. b. $1056 unfavorable. c. $1200 favorable. d. $1056 fa
- The following data relate to labor costs for the production of 5,700 cellular telephones: Actual: 3,870 hrs. at $15.9 Standard: 3,810 hrs. at $16.1 Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance.
- a) Calculate the direct labor price variance. b) Calculate the direct labor quantity variance. c) Calculate the total direct labor variance. d) Explain what might have caused the variances.
- The formula to compute the direct labor rate variance is to calculate the difference between: a. Actual costs + (Actual hours * Standard rate) b. Actual costs - Standard cost c. (Actual hours * Standard rate) - Standard costs d. Actual costs - (Actual
- The difference between actual costing and normal costing is a) normal costing uses budgeted indirect-costs. b) normal costing uses actual quantities of direct-costs. c) actual costing uses actual quantities of cost-allocation bases. d) actual costing uses
- Variable overhead efficiency variance is the difference between actual hours worked at standard rate and standard hours allowed at standard rate. The formula of variable overhead efficiency variance is given below: Variable overhead efficiency variance =
- When preparing the direct labor budget,[{\Blank}] A. the actual direct labor cost per hour must be known B. budgeted units to be produced are multiplied by direct labor cost per hour to determine budgeted direct labor cost C. direct labor hours needed for
- The following data relate to direct labor costs for the current period: Standard costs 36,000 hours at $22.00 Actual costs 35,000 hours at $23.00. What is the direct labor time variance?
- The following data relate to direct labor costs for the current period: Standard costs 7, 500 hours at $11.60 Actual costs 6,000 hours at $12.00 What is the direct labor time variance? $3,000 favora
- Is $20 per direct labor hour. If the actual direct labor payroll was $148960 for 7600 direct labor hours worked, the direct labor price (rate) variance is A. $3040 unfavorable. B. $3800 favorable.
- The standard rate of pay is $20 per direct labor hour. If the actual direct labor payroll was $94,080 for 4,800 direct labor hours worked, the direct labor price (rate) variance is: a. $1,920 favorable. b. $2,400 unfavorable. c. $,2400 favorable. d. $1,92
- Which one of the following is the difference between the actual hourly wage rate and the standard hourly wage rate, multiplied by the actual number of direct labor hours worked during a period? A. Direct labor usage variance. B. Direct labor rate varian
- The following data relate to direct labor costs for the current period: Standard hours 6,000 hours @ $11.50 Actual costs 7,500 hours @ $12.00 5. What is the direct labor rate variance? $15,000 unfavor
- The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 2,300 units, the actual direct labor cost was $68,800 for 4,300 direct labor hours worked, the total direct labor variance is: a. $125 unfavorable. b. $200 f
- Use the following data to find the direct labor cost variance. Direct labor standard (4 hrs. @ $5/hr.), $20 per unit. Actual hours worked per unit, 3.5 hours. Actual units produced, 3,800 units. A
- At 9,000 direct labor hours, the flexible budget for indirect materials is $27,000. If $28,000 of indirect materials costs are incurred at 9,200 direct labor hours, the flexible budget report should show the following difference for indirect materials: a
- Complete the table below for the missing variances. Total flexible budget product cost variance (f) Total direct materials variance Total direct labor variance Total manufacturing overhead variance (a) (b) (e) Direct materials cost variance Direct materi
- The following data relate to labor costs for the production of 3,700 cellular telephones: Actual 2,530 hrs. at $13.9 Standard 2,490 hrs. at $14.2 Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance.
- The most fundamental variance analysis compares: a. standard material prices with actual material prices. b. standard direct labor rates with actual direct labor rates. c. budgeted sales revenue with actual sales revenue. d. budgeted operating income
- The following data relate to labor costs for the production of 7,200 cellular telephones: Actual4,840 hrs. at $12.8 Standard 4,760 hrs. at $13.1 Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance.
- Direct labor variance is the difference between the standard cost and the actual cost of production. Considering this, answer the questions that follow: What effect, if any, would you expect poor qua
- The following data relate to direct labor costs for the current period: Standard costs36,000 hours at $22.50 Actual costs35,000 hours at $23.00 What is the direct labor time variance? a. $22,500 favor
- The following data relate to labor cost for production of 3,500 cellular telephones: Actual 2,340 hrs. at $15.60 $36,504 Standard 2,380 hrs. at $15.20 $36,176 a. Determine the direct labor rate variance, direct labor time variance, and total direct labor
- The per-unit standards for direct labor are 1.5 direct labor hours at 15 dollars per hour. If in producing 2,300 units, the actual direct labor cost was 46,000 dollars for 3,000 direct labor hours wor
- If the wage rate paid per hour differs from the standard wage rate per hour for direct labor, the variance is termed: a. variable variance b. rate variance c. quantity variance d. volume variance
- The standard direct labor cost per unit for a company was $39 (= $26 per hour X 1.5 hours per unit). During the period, actual direct labor costs amounted to $239, 300, 9, 100 labor-hours were worked
- The standard direct labor cost per unit for a company was $39 ($26 per hour x 1.5 hours per unit). During the period, actual direct labor costs amounted to $239,300, 9,100 labor-hours were worked, an
- An unfavorable direct labor rate variance indicates which of the following? A. Both Actual Quantity (AQ) and the actual cost of direct labor hours exceeded standard quantity and standard cost of hours for actual output. B. The Actual Quantity (AQ) of dire
- Which of the following is not typical of traditional costing systems: a) use of a single predetermined overhead rate. b) use of direct labor hours or direct labor cost to assign overhead. c) assumption of correlation between direct labor and incurrence of
- The following data relate to direct labor costs for March: Rate: standard, $12.00; actual, $12.25 Hours: standard, 18,500; actual, 17,955 Units of production: 9,450 Calculate the direct labor time variance: a. $6,540.00 unfavorable b. $6,540.00 favor
- If the actual labor rate exceeds the standard labor rate and the actual labor hours exceed the number of hours allowed, the labor rate variance and labor efficiency variance will be A) Labor rate variance - favorable & Labor efficiency variance - favorab
- The following data relate to labor costs for the production of 22,000 cellular telephones: Actual: 4,220 hours at $44.50 Standard: 4,160 hours at $46 a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost vari
- Budgeted direct labor is $24,000 based on 2,000 hours of labor. What would be the flexible budget amount for labor if we used 2,200 hours of labor? (show your work)
- The standard direct labor cost per unit for a company was $27 (= $18 per hour times 1.5 hours per unit). During the period, actual direct labor costs amounted to $178,700, 9,800 labor-hours were worke
- The primary difference between absorption and variable costing is that variable costing treats a. Only direct materials and direct labor as product cost. b. Direct materials, direct labor, the variable portion of manufacturing overhead, and an allocated
- At 18,000 direct labor hours, the flexible budget for indirect materials is $36,000. If $37,400 are incurred at 18,400 direct labor hours, the flexible budget report should show the following difference for indirect materials: A. $1,400 unfavorable B. $1,
- Manufacturing overhead is applied based on budgeted direct labor hours. The direct labor budget indicates that 5,400 direct labor hours will be required during the year. The variable overhead rate is $3.40 per direct labor hour. The company's budgeted fix
- The standard overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 fixed factory overhead) based on a 100% capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of
- Budgeted direct labor hours are multiplied to direct labor cost rate to calculate: A. expected total direct labor cost B. budgeted total direct labor cost C. budgeted total indirect labor cost D. expected labor hours
- The following data relate to labor cost for production of 5,500 cellular telephones: a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Ente
- The following data relate to labor cost for production of 6,900 cellular telephones: a) Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Ent
- The following data relate to labor cost for production of 5,900 cellular telephones: a) Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Ente
- The manufacturing overhead budget at Mahapatra Corporation is based on budgeted direct labor hours. The direct labor budget indicates that 7,900 direct labor hours will be required in May. The variable overhead rate is $9.50 per direct labor hour. The com
- The manufacturing overhead budget at Mahapatra Corporation is based on budgeted direct labor hours. The direct labor budget indicates that 7,000 direct labor hours will be required in May. The variable overhead rate is $8.80 per direct labor hour. The com
- If overhead is applied to production using direct labor hours and the direct labor efficiency variance is favorable, then the variable overhead efficiency variance is: a. favorable b. unfavorable c. either favorable or unfavorable. d. neither favorabl
- The per unit standard for direct labor was 1.5 DL hours at 15 per hour if producing 2400 units, the actual direct labor costs 46,000. For 3000 DL hours worked. The total direct labor variance is: A. 2400 Unfavorable. B. 8000 favorable. C. 5000 Unfavora
- If overhead is applied to production using direct labor hours and the direct labor efficiency variance is favorable, then the variable overhead efficiency variance is: A) either favorable or unfavorable. B) unfavorable. C) favorable. D) neither favora
- The standard direct labor cost per unit for a company was $27 ($18 per hour x 1.5 hours per unit). During the period, actual direct labor costs amounted to $178,700, 9,800 labor-hours were worked, and 5,800 units were produced. Required: Compute the d
- July's direct manufacturing labor flexible-budget variance is: a. $750.00 unfavorable b. $262.50 favorable c. $487.50 unfavorable d. none of the above Data: Sawyer Industries Inc. (SII) developed standard costs for direct material and direct labor.
- Which of the following is not a flexible budget variance? A) total fixed overhead variance B) total variable overhead variance C) total direct materials variance D) total direct labor variance