The Rockmart Construction Company delivers dirt and stone from local quarries to its construction...
Question:
The Rockmart Construction Company delivers dirt and stone from local quarries to its construction sites. A new truck that was purchased for a cost of $118,000 at the beginning of the year was expected to deliver 118,000 tons over Its useful life.
The following Is a breakdown of the tons delivered during the year to each construction site:
Construction Sites | A | B | C | D |
Tons Delivered | 1,800 | 3,300 | 3,800 | 1,300 |
How much truck depreciation should be allocated to Site D?
a. $15,039
b. $1,300
c. $1,180
d. None of the above answers are correct.
Overhead Allocation:
Overhead costs cannot be traced to the units produced physically and it is therefore allocated using overhead allocation rates. These rates should be relevant to the way in which the overhead is incurred.
Answer and Explanation: 1
Become a Study.com member to unlock this answer! Create your account
View this answer
The correct option is b. $1,300 .
We must calculate the depreciation rate for the new truck and then apply that to the tons delivered to...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:

from
Chapter 7 / Lesson 5Overhead in activity-based costing systems is determined by including all the different actions taken in production. See the formula used to calculate overhead in this method demonstrated through two example scenarios.
Related to this Question
- The Flintstone Construction Company delivers dirt and stone from local quarries to its construction sites. A new truck that was purchased for a cost of $120,000 at the beginning of the year was expected to deliver 200,000 tons over its useful life. The fo
- The Step On It Corporation delivers dirt and stone from local quarries to its construction sites. A new truck that was purchased for a cost of $234,000 at the beginning of the year was expected to deliver 200,000 tons over its useful life. The following i
- Smith Concrete Company owns enough ready-mix trucks to deliver up to 100,000 cubic yards of concrete per year (considering each truck's capacity, weather, and distance to each job). Total truck deprec
- ASD Company purchased land as a factory site. An old building on the property was demolished, and construction began on a new building. Costs incurred during the first year are listed below: - Land p
- Mo Lambert formed a corporation to provide concrete construction work. His jobs typically involve building parking lots, drives, and foundations. Mo provided the following information about transacti
- Cheyenne Co. purchased land as a factory site for $504,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $52,920 to raze the old buildings and sold salvaged lumber and brick for
- Metlock Co. purchased land as a factory site for $456,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,880 to raze the old buildings and sold salvaged lumber and brick for
- Sheffield Co. purchased land as a factory site for $496,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $52,080 to raze
- The Italian Pizza Company purchased land as a factory site for $71,000. Prior to the construction of the new building, the land had to be cleared of trees and brush. Construction costs incurred during the first year are listed below: Land clearing costs $
- China Express purchased land for $140,000. Prior to construction on the new building, the land had to be cleared of trees and brush. Construction costs incurred during the first year are listed below: [TABLE] Required: Determine the amounts that should b
- Splish Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the
- At the beginning of 2021, Terra Lumber Company purchased a timber tract from Boise Cantor for $3,340,000. After the timber is cleared, the land will have a residual value of $700,000. Roads to enable logging operations were constructed and completed on Ma
- In 2011, the Marion Company purchased land containing a mineral for $ 1,600,000. Additional cost of $600,000 were incurred to develop the mine. Geologists suggest that 400,000 tons of ore would be ext
- Coal Company purchased the coal rights in an area for $4,050,000. They estimated that the area contained 9,000,000 tons of coal. The first year of operations in the area yielded 110,000 tons of coal. What is the depletion cost per ton of coal?
- Petoskey Stone Quarry Inc. (PSQ), a calendar-year, accrual-method C corporation, provides landscaping supplies to local builders in northern Michigan. PSQ has always been a family-owned business and h
- The city of Littleton donated a building and land to the Hetting Co. without charge. The agreement provided that the company employ 350 people for 10 years. The land was appraised at $65,000 and the building at $44,000. 1. Prepare the journal entry to re
- Stone Age Concrete, Inc. purchased cement manufacturing equipment valued at $344,000 on March 14, 2001. The equipment is used for business 100% of the time. As the accountant, you have elected to take the maximum section 179 deduction. a.) What is the ba
- During 2014, a company purchased a mine at a cost of $3,000,000. The company spent an additional $600,000 getting the mine ready for its intended use. It is estimated that 300,000 tons of mineral can
- CC Coal Company purchased the coal rights in an area for $4,050,000. They estimated that the area contained 9,000,000 tons of coal. The first year of operations in the area yielded 110,000 tons of coal. 1. What is the depletion cost per ton of coal? 2.
- Skyline Corporation has decided to expand its operations and has purchased land in Salina for the construction of a new manufacturing plant. The following costs were incurred in purchasing the property and constructing the building: Land purchase price $1
- On March 31, 2016, M. Belotti purchased the right to remove gravel from an old rock quarry. The gravel is to be sold as a roadbed for highway construction. The cost of the quarry rights was $333,000, with an estimated salable rock of 37,000 tons. During 2
- On March 31, 2013, M. Belotti purchased the right to remove gravel from an old rock quarry. The gravel is to be sold as roadbed for highway construction. The cost of the quarry rights was $164,000, with estimated salable rock of 20,000 tons. During 2013,
- On March 31, 2016, M. Belotti purchased the right to remove gravel from an old rock quarry. The gravel is to be sold as a roadbed for highway construction. The cost of the quarry rights was $216,000, with the estimated salable rock of 30,000 tons. During
- a. In 2016, the Marion Company purchased land containing a mineral mine for $1,600,000. b. Additional costs of $600,000 were incurred to develop the mine. c. Geologists estimated that 400,000 tons of
- From a building in downtown Newburg, the Newburg Flyers operate a major sports franchise. The building was built in 1940 at a cost of $5,000,000 and is fully depreciated so that it is shown on the company's balance sheet at a nominal value of $1. The land
- A company purchased land for $540,000 cash. The real estate brokers' commission was $20,000 and $47,000 was spent for demolishing an old building on the land before construction of a new building could start. Under the historical cost principle, the cost
- The Newburg Flyers operate a major sports franchise from a building in downtown Newburg. The building was built in 1940 at a cost of $5,000,000 and is fully depreciated so that it is shown on the company's balance sheet at a nominal value of $1. The land
- Flint Realty Corporation purchased a tract of unimproved land for $51,000. This land was improved and subdivided into building lots at an additional cost of $28,000. These building lots were all of th
- Flint Realty Corporation purchased a tract of unimproved land for $55,000. This land was improved and subdivided into building lots at an additional cost of $27,000. These building lots were all of th
- Carolina Company purchased a building and the land on which the building is situated for a total cost of $988,800 cash. The land was appraised at $284,280 and the building at $852,840. Required: a. Wh
- Roster Roofing Ltd. is planning on purchasing two new trucks for its operation. The operating cost of these trucks is expected to be lower per mile than the trucks it is trading in. The owner is trying to determine if the company would be better off keepi
- On March 1, 2014, Newton Company purchased land for an office site by paying $1,800,000 cash. Newton began construction on the office building on March 1. The following expenditures were incurred for construction: tabletheadtrthDate/ththExpenditures/th/tr
- ABC Company purchased a piece of land with a preexisting building on it for a price of $250,000. In order to prepare the land for future construction, the old building was demolished at a cost of $15,000. The amount of scrap material that resulted from th
- Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, b
- A company purchased land for $90,000 cash. Real estate brokers' commission was $5,000 and $7,000 was spent for demolishing an old building on the land before construction of a new building could start. Under the cost principle, the cost of land would be r
- A company purchased land for $70,000 cash. Real estate brokers' commission was $5,000 and $7,000 was spent for demolishing an old building on the land before construction of a new building could start. Under the cost principle, the cost of land would be r
- In 2016, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of $568,000 were incurred to develop the mine. Geologists estimated that 600,000 tons of ore would be extracted. After the ore is removed, the land will
- Monty Co. purchased land as a factory site for $448,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,040 to raze the
- On March 31, 2016, M. Blackstone purchased the right to remove gravel from an old rock quarry. The gravel is to be sold as a roadbed for highway construction. The cost of the quarry rights was $164,000, with the estimated salable rock of 20,000 tons. Duri
- Preston Concrete is a major supplier of concrete to residential and commercial builders in the Pacific Northwest. The company's general pricing policy is to set prices at $122 per cubic yard. Deliveries for 2019 were 400,000 cubic yards, and total costs w
- Preston Concrete is a major supplier of concrete to residential and commercial builders in the Pacific Northwest. The company's general pricing policy is to set prices at $121 per cubic yard. Deliveries for 2018 were 400,000 cubic yards. Total costs were:
- Garcia Inc., a small construction company had several transactions relating to its long-lived assets during the year: a. The company purchased a new truck from the local truck dealer. The list price was $30,000. They traded-in their old truck and gave th
- Borden Company incurred the following costs to acquire and prepare land for a new parking lot: purchase price for land, cost to clear the land, cost of paving, lighting for the parking lot, and landscaping for the parking lot. How should the company deter
- In 2016, the Marion Company purchased land containing a mineral mine for $2,050,000. Additional costs of $843,000 were incurred to develop the mine. Geologists estimated that 490,000 tons of ore would
- In 2013, the Marion Company purchased land containing a mineral mine for $1,400,000. Additional costs of $538,000 were incurred to develop the mine. Geologists estimated that 360,000 tons of ore would
- On March 31, 2016, M. Belotti purchased the right to remove gravel from an old rock quarry. 1. The gravel is to be sold as a roadbed for highway construction. 2. The cost of the quarry rights was $210,600, with the estimated salable rock of 27,000 tons. 3
- Windhoek Mine, Ltd, of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made
- Blue Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $150,000 in cash. In addition, it paid $2,400 in surveying costs and $3
- In 2016, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of $564,000 were incurred to develop the mine. Geologists estimated that 600,000 tons of ore would
- In 2016, the Marion Company purchased land containing a mineral mine for $1,850,000. Additional costs of $745,000 were incurred to develop the mine. Geologists estimated that 450,000 tons of ore would
- In 2021, the Marion Company purchased land containing a mineral mine for $1,700,000. Additional costs of $667,000 were incurred to develop the mine. Geologists estimated that 420,000 tons of ore would be extracted. After the ore is removed, the land will
- Prompt Parcel Service operates a fleet of delivery trucks in a large metropolitan area. A careful study by the company's cost analyst has determined that, if a truck is driven 72,000 kilometres during
- Prompt Parcel Service operates a fleet of delivery trucks in a large metropolitan area. A careful study by the company's cost analyst has determined that if a truck is driven 100,000 kilometres during
- Windhoek Mines, Ltd, of Namibia, is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made
- Landmark Coal operates a mine. During July, the company obtained 500 tons of ore, which yielded 250 pounds of gold and 63,100 pounds of copper. The joint cost related to the operation was $500,000. Go
- Landmark Coal operates a mine. During July, the company obtained 500 tons of ore, which yielded 250 pounds of gold and 63,400 pounds of copper. The joint cost related to the operation was $500,000. Go
- Speedy Parcel Service operates a fleet of delivery trucks in a large metropolitan area. A careful study by the company's cost analyst has determined that if a truck is driven 120,000 miles during a ye
- The Adams Construction Company is bidding on a project to install a large flood drainage culvert from Dandridge to a distant lake. a. If they bid $2,000,000 for the job, what is the benefit-cost rati
- Forda Lumber Company owns a 9,450-acre tract of timber purchased in 2007 at a cost of $1,755 per acre. At the time of purchase, the land was estimated to have a value of $405 per acre without the timb
- Forda Lumber Company owns a 7,000-acre tract of timber purchased in 2007 at a cost of $1,300 per acre. At the time of purchase, the land was estimated to have a value of $300 per acre without the timb
- At the beginning of 2011, Terra Lumber Company purchased a timber tract from Boise Cantor for $3,200,000. After the timber is cleared, the land will have a residual value of $600,000. Roads to enable
- A highway contractor is considering buying a new trench excavator that costs $300,000 and can dig a 3-foot-wide trench at the rate of 16 feet per hour. The annual number of feet to dig each year is 6,
- A company acquired some land for $80,000 to construct a new office complex. Legal fees paid were $2,300, delinquent taxes assumed were $3,400, and $5,850 was paid to remove an old building from which salvaged materials sold for $950. What is the cost basi
- Hollings Company sells and delivers office furniture in the Rocky Mountain area. The costs associated with the acquisition and annual operation of a delivery truck are given below: Insurance $1,600 Licenses $250 Taxes (vehicle) $150 Garage rent for parki
- A construction company is bidding on a project to install a large flood drainage culvert from Dandridge to a distant lake. If they bid $1,900,000 for the job, what is the benefit-cost ratio in view of
- Forda Lumber Company owns a 13,580-acre tract of timber purchased in 2007 at a cost of $2,522 per acre. At the time of purchase, the land was estimated to have a value of $582 per acre without the tim
- Novak Co. purchased land as a factory site for $448,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,040 to raze the
- Headland Corp. is a medium-sized corporation specializing in quarrying stone for building construction. The company has long dominated the market, at one time achieving a 70% market penetration. Durin
- Italian Bread Company purchased land as a factory site for 61,200. An old building on the property was demolished and construction began on a new building. Costs incurred during tho first year are lis
- The Italian Bread Company purchased land as a factory site for $70,000. An old building on the property was demolished, and construction began on a new building. Costs incurred during the first year a
- Allen Company purchased land as a factory site for $80,000. The process of tearing down two old buildings
- Manzeck Company operates a snow-removal service. The company owns five trucks, each of which has a snow plow in the front to plow driveways and a snowthrower in the back to clear sidewalks. Because plowing snow is very tough on trucks, the company incurs
- Automated Audit Company Co. (AACC) purchased land as a factory site for $1,700,000. AACC paid $250,000 to tear down two buildings on the land. The salvage was sold for $3,800. Legal fees of $150,550 were paid for the title investigation and making the
- Martin Buber Co. purchased land as a factory site for $686,800. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $72,114 to raze the old buildings and sold salvaged lumber and bric
- Martin Buber Co. purchased land as a factory site for $865,200. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $90,846 to raze the old buildings and sold salvaged lumber and bric
- Laural Company paid USD 840,000 cash for real property consisting of a tract of land and a building. The company intended to remodel and use the old building. To allocate the cost of the property acquired, Laural had the property appraised. The appraised
- Crane Company purchased a machine on July 1, 2018, for $33,040. Crane paid $236 in title fees and county property tax of $148 on the machine. In addition, Crane paid $590 shipping charges for delivery, and $561 was paid to a local contractor to build and
- A company purchased land for $80,000 cash. The real estate brokers' commission was $6,000 and $9,500 was spent for demolishing an old building on the land before construction of a new building could start. Under the cost principle, what would the cost of
- Martin Buber Co. purchased land as a factory site for $436,800. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $45,864 to raze the old buildings and sold salvaged lumber and brick
- Martin Buber Co. purchased land as a factory site for $869,600. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $91,308 to raze the old buildings and sold salvaged lumber and brick
- Martin Buber Co. purchased land as a factory site for $758,400. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $79,632 to raze the old buildings and sold salvaged lumber and brick
- Stanislaw Timber Company owns 9,000 acres of timberland purchased in 2003 at a cost of $1,400 per acre. At the time of purchase, the land without the timber was valued at $400 per acre. In 2004, Stanislaw built fire lanes and roads, with a life of 30 year
- Stone Age Concrete, Inc. purchased cement manufacturing equipment valued at $344,000 on March 14, 2001. The equipment is used for business 100% of the time. As the accountant, you have elected to take
- Forda Lumber Company owns a 7,000-acre tract of timber purchased in 2007, at a cost of $1,300 per acre. At the time of purchase, the land was estimated to have a value of $300 per acre without the timber. Forda Lumber Company has not logged this tract sin
- Keaubie Co. purchased land at a cost of $250,000 cash. The property had a building on it that was demolished at a cost of $10,000. Proceeds from salvaged materials from the demolition amounted to $2,100. Attorney's fees were $3,100 and the real estate bro
- Martin Buber Co. purchased land as a factory site for $454,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,670 to raze the old buildings and sold salvaged lumber and bric
- Crane Co. purchases land and constructs a service station and car wash for a total of $517500. At January 2, 2018, when construction is completed, the facility and land on which it was constructed are sold to a major oil company for $670000 and immediatel
- Johnson Construction Materials Company has a sales office which sells concrete culvert pipe to 33) property developers. The sales office is a revenue center and must prepare a monthly performance repo
- Abby Inc produces granite grave stones. Each monument typically requires 300 pounds of granite. The standard cost for granite is estimated at $150 per ton (2,000 pounds). During a recent month, 200 monuments were constructed. The company purchased and use
- Tennecott Mining Company purchased a tract of land with estimated copper ore deposits totaling 800,000 tons. The purchase price for the land was $2.2 million. During the first year of operation, Tennecott mined and sold 90,000 tons of ore. During the seco
- Flint Company built a warehouse for $696,000. It could have purchased the building for $858,400. The controller made the following entry. Buildings $858,400 Cash $696,000 Profit on Construction $162,400 Prepare the entry that should have been made at the
- Crane Company owns an 8,190-acre tract of timber purchased in 2003 at a cost of $1,521 per acre. At the time of purchase, the land was estimated to have a value of $351 per acre without timber. Crane Company has not logged this tract since it was purchase
- Intermountain Delivery Company acquired an adjacent lot to construct a new warehouse, paying $100,000 and giving a short-term note for $700,000. Legal fees paid were $5,000, delinquent taxes assumed were $18,500, and fees paid to remove an old building f
- Intermountain Delivery Company acquired an adjacent lot to construct a new warehouse, paying $100,000 and giving a short-term note for $700,000. Legal fees paid were $5,000, delinquent taxes assumed were $18,500, and fees paid to remove an old building fr
- Wind Mines is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made, and it is expected that the following cash flows would be associated with o
- The Valuation Premise Company (VPC) acquires land in a business combination. The land is currently being developed for industrial use as a site for a manufacturing facility. Nearby sites were recently developed for residential high-rise condominiums. Base
- Automated Audit Company Co. (AACC) purchased land as a factory site for $1,700,000. AACC paid $250,000 to tear down two buildings on the land. The salvage was sold for $3,800. Legal fees of $150,550 were paid for the title investigation and making the pur
- Automated Audit Company Co. (AACC) purchased land as a factory site for $1,700,000. AACC paid $250,000 to tear down two buildings on the land. The salvage was sold for $3,800. Legal fees of $150,550 were paid for the title investigation and making the p
- ABC Country Club has acquired a lot to construct a clubhouse. ABC had the following costs related to the construction: Architects Fees $20,000 Construction Labor 80,000 Engineers Fees 15,000 Fences around building 9,000 Grading and leveling 10,000 Insuran
- Windhoek Mines Ltd. of Namibia is contemplating the purchase of equipment to exploit a mineral deposit on land to which the company has mineral rights. An engineering and cost analysis has been made a