The Manufacturing Company recorded overhead costs of $14,182 at an activity level of 4,200...
Question:
The Manufacturing Company recorded overhead costs of $14,182 at an activity level of 4,200 machine hours and $8,748 at 2,300 machine hours. What is the total estimated cost for 3,500 machine hours using the high-low method to estimate the cost equation?
A. $10,178
B. $9,606
C. $12,180
D. $8,788
High-Low Method:
The high-low method of accounting is used to bifurcate the total cost into fixed cost and variable cost. The first step is to determine the variable cost per unit by considering the total cost at the higher level of activity and the total cost at a lower level of activity. The second step is to determine the fixed cost by reducing the variable cost from the total cost.
Answer and Explanation: 1
Become a Study.com member to unlock this answer! Create your account
View this answer
Correct answer: Option C) $12,180.
Explanation:
Under the high-low method:
- Variable cost per unit = (Total cost at the highest level of activity -...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:

from
Chapter 22 / Lesson 29Understand the high-low method in accounting. Learn the formulas for the high-low method. Learn how to compute variable cost per unit, fixed cost, and cost model.
Related to this Question
- Foster Co. uses a predetermined overhead rate based on machine hours. This predetermined rate was based on a cost formula that estimated $745,500 of total manufacturing overhead for an estimated activity level of 12,500 machine hours for the factory. The
- A company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $310,700 for the year, and machine usage is estimated at 127,000 hours. For the year, $327,498 of overhead costs are incurred and 131
- Ikard Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $292,552 for the year, and machine usage is estimated at 126,100 hours. For the year, $399,060 of overhead costs are incurred and
- At an activity level of 9,300 machine-hours in a month, Falks Corporation's total variable production engineering cost is $829,560 and its total fixed production engineering cost is $192,960. What would be the total production engineering cost per machine
- At an activity level of 4,000 machine-hours in a month, Curt Corporation's total variable production engineering cost is $154,200 and its total fixed production engineering cost is $129,000. What would be the total production engineering cost per machine-
- Molding Fabrication Total Machine-hours 24,000 34,000 58,000 Fixed manufacturing overhead costs $ 730,000 $220,000 $950,000 Variable manufacturing overhead cost per machine-hour $5.50 $5.50 During th
- Machine-hours required to support estimated production 152,000 Fixed manufacturing overhead cost $651,000 Variable manufacturing overhead cost per machine-hour $4.10 Required: 1. Compute the plantwid
- At an activity level of 9,100 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $765,310 and its total fixed production engineering cost is $224,070. Assume that this level of activity is within the relevant rang
- At an activity level of 9,300 machine hours in a month, Nooner Corporation's total variable production engineering cost is $839,790 and its total fixed production engineering cost is $237,820. Assume that this level of activity is within the relevant rang
- At an activity level of 4,000 machine-hours in a month, Curt Corporation's total variable production engineering cost is $154,200, and its total fixed production engineering cost is $129,000. What would be the total production engineering cost per unit, b
- At an activity level of 8,600 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $734,440 and its total fixed production engineering cost is $154,000. What would be the total production engineering cost per unit,
- At an activity level of 9,300 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $766,320 and its total fixed production engineering cost is $191,040. What would be the total production engineering cost per unit,
- At an activity level of 10,000 machine hours in a month, Nooner Corporation's total variable production engineering cost is $837,000 and its total fixed production engineering cost is $276,150. What would be the total production engineering cost per unit
- At an activity level of 8,700 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $744,720 and its total fixed production engineering cost is $181,560. What would be the total production engineering cost per unit,
- At an activity level of 9,700 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $810,435, and its total fixed production engineering cost is $193,050. What would be the total production engineering cost per unit,
- At an activity level of 9,800 machine hours in a month, Nooner Corporation's total variable production engineering cost is $888,860 and its total fixed production engineering cost is $254,430. What would be the total production engineering cost per unit,
- The Chambers Manufacturing Company recorded overhead costs of $14,182 at an activity level of 4,200 machine hours and $8,748 at 2,300 machine hours. The records also indicated that an overhead of $9,730 was incurred at 2,600 machine hours. What is the var
- At an activity level of 9,000 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $796,500 and its total fixed production engineering cost is $235,290. Wha
- At an activity level of 9,900 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $882,090 and Its total fixed production engineering cost is $196,000. What
- At an activity level of 8,900 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $760,060 and its total fixed production engineering cost is $152,880. What wo
- You have calculated, using the high-low method, a variable cost per machine hour of $0.80 for your production power costs. Power costs at 6,000 machine hours are $5,400; at 9,000 machine hours, they are $7,800. What are the total fixed costs that you woul
- Job 593 was recently completed. The following data have been recorded on its job cost sheet: (Table). The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $21 per machine-hour. The total cost tha
- Wangerin Corporation applies overhead to products based on machine hours. 1. The denominator level of activity is 8,900 machine hours. 2. The budgeted fixed manufacturing overhead costs are $328,410. In April, the actual fixed manufacturing overhead cost
- A manufacturer estimates its factory overhead costs to be $30,000 and machine hours to be 4,000 for the year. If the actual hours worked on production total 3,800 and the actual factory overhead costs are $28,000, what is the amount of the over- or undera
- The Chambers Manufacturing Company recorded overhead costs of $14,313 at an activity level of 4,250 machine hours and $8,825 at 2,350 machine hours. The records also indicated that an overhead of $9,762 was incurred at 2,625 machine hours. What is the va
- Allocation base Machine-hours Estimated manufacturing overhead cost $147,000 Estimated total amount of the allocation base 35,000 machine- hours Actual manufacturing overhead cost $133,800 Actual tota
- At the end of the year, actual manufacturing overhead costs were $120,000, and applied manufacturing overhead costs were 136,500. If the denominator activity for the year was 20,000 machine hours, and if 21,000 standard machine hours were allowed for the
- Manufacturing overhead is allocated to products based on the number of machine hours required. In a year when 20,000 machine hours were anticipated, costs were budgeted at $125,000. If a product requires 7,000 machine hours, how much manufacturing overhea
- Manufacturing overhead is allocated to products based on the number of machine hours required. In a year when 20,000 machine hours were anticipated, costs were budgeted at $125,000. If a product requires 8,000 machine hours, how much manufacturing overhea
- Data Allocation base Machine-hours Estimated manufacturing overhead cost $560,900 Estimated total amount of the allocation base 79,000 machine-hours Actual manufacturing overhead cost $563,700 Actual
- Data Allocation base Machine-hours Estimated manufacturing overhead cost $279,300 Estimated total amount of the allocation base 49,000 machine-hours Actual manufacturing overhead cost $266,000 Actual
- The Chambers Manufacturing Company recorded overhead costs of $14,182 at an activity level of 4,200 machine hours and $8,748 at 2,300 machine hours. The records also indicated that overhead of $9,730
- The Wiscow Manufacturing Company recorded overhead costs of $18,122 at an activity level of 5,200 machine hours and $10,038 at 2,800 machine hours. The records also indicated that an overhead of $10,095 was incurred at 3,100 machine hours. What is the tot
- The Wiscow Manufacturing Company recorded overhead costs of $21,500 at an activity level of 5,000 machine hours and $8,000 at 2,500 machine hours. The records also indicated that overhead of $10,000 was incurred at 4,200 machine hours. Using the high-low
- At an activity level of 9,300 machine-hours in a month, Nooner Corporation's total variable production engineering cost is $839,790 and its total fixed production engineering cost is $237,820. What w
- Work A Work B Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed manufacturing overhead 11,500 15,900 27,400 Estimated variable manufacturing overhead per machine-hour 2.00 2.80 What is the plantwide predetermined overhead r
- Marigold company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are estimated to total $347,325 for the year, and machine usage is estimated at 126,300 hours. For the year, $275,125 of overhead costs are incurred
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $280,896 for the year, and machine usage is estimated at 125,400 hours. For the year, $400,896 of overhead costs are incurred an
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $326,772 for the year, and machine usage is estimated at 125 200 hours. For the year, $363,320 of overhead costs are incurred and
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $280,896 for the year, and machine usage is estimated at 125,400 hours. For the year, $400,896 of overhead costs are incurred and
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $292,552 for the year, and machine usage is estimated at 126,100 hours. For the year, $413,432 of overhead costs are incurred and
- Ikerd Company applies manufacturing overhead on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the ye
- Gammaro Company uses normal costing. It allocates manufacturing overhead costs using a budgeted rate per machine hour. The following data are available for 2014: Budgeted manufacturing overhead costs $4,200,000 Budgeted machine-hours 175,000 Actual manufa
- At the beginning of the year, Scaled Manufacturing estimates annual overhead costs to be $1,200,000 and that 300,000 machine hours will be operated. Using machine hours as a base, the amount of overhead applied during the year if actual machine hours for
- A company's manufacturing overhead includes $7.10 per machine hour for variable manufacturing overhead and $207,000 per period for fixed manufacturing overhead. What is the predetermined overhead rate for the denominator level of activity of 4,600 machine
- At the end of the year, actual manufacturing overhead costs were $120,000 and applied manufacturing overhead costs were $160,175. If the denominator activity for the year was 20,000 machine-hours, and if 21,500 standard machine-hours were allowed for the
- The estimated allocation base is 25,000 machine hours and the estimated total manufacturing overhead cost is $71,500. The predetermined overhead rate to be applied to the jobs is: a. $2.86 per machine hour b. $2.86 per job c. $0.035 per machine hour
- The Wiscow Manufacturing Co. recorded overhead costs of $21,500 at an activity level of 5,000 machine hours and $8,000 at 2,500 machine hours. The records also indicated that overhead of $10,000 was incurred at 4,200 machine hours. Using the high-low meth
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred and
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. Fo
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $294,138 for the year, and machine usage is estimated at 125,700 hours. F
- Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $276,660 for the year, and machine usage is estimated at 125,300 hours. For the year, $296,534 of overhead costs are incurred an
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $276,980 for the year, and machine usage is estimated at 125,900 hours. Fo
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $280,896 for the year, and machine usage is estimated at 125,400 hours. Fo
- Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $341,523 for the year, and machine usage is estimated at 125,100 hours. Fo
- The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 33,000 machine-hours and incur $169,950 in manufacturing overhea
- The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 43,000 machine-hours and incur $197,800 in manufacturing overhea
- Calculating Manufacturing Overhead Rates Glassman Company accumulated the following data for 2016 Milling Department manufacturing overhead Finishing Department manufacturing overhead Machine hours us
- Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $330,200 for the year, and machine usage is estimated at 127,000 hours. For the year, $349,663 of overhead costs are incurred an
- Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $275,660 for the year, and machine usage is estimated at 125,300 hours. For the year $296,534 of overhead costs are incurred and
- Duggan Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $300,960 for the year, and machine usage is estimated at 125,400 hours. For the year, $322,290 of overhead costs are incurred an
- Duggan Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $304,560 for the year, and machine usage is estimated at 126,900 hours. For the year, $323,682 of overhead costs are incurred an
- Duggan company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $341,010 for the year, and machine usage is estimated at 126,300 hours. For the year, $363,036 of overhead costs are incurred an
- Strong Company applies overhead based on machine hours. At the beginning of 20x1, the company estimated that manufacturing overhead would be $792,000 and machine hours would total 24,000. By 20x1 year
- Thomas Company uses a predetermined overhead rate of $32 per machine hour. Estimated machine hours at the beginning of the year were 14,000 and actual machine hours at the end of the year were 14,200. Estimated total manufacturing overhead costs at the be
- Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $325,000 for the year, and machine usage is estimated at 125,000 hours. F
- Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $316,000 for the year, and machine usage is estimated at 126,400 hours. F
- Company X allocates overhead based on machine hours. It estimated the overhead cost for the year to be $420,000. Estimated machine hours were 50,000. Actual hour costs for the year were 46,000 machine hours and $380,000 of overhead. a) Calculate the over
- The cost formulas of a manufacturing overhead costs are given below. The costs cover a range of 8,000 to 10,000 machine-hours. Overhead costs include: Supplies $0.20 per machine hour Indirect labor $5,000 plus $0.25 per machine hour Utilities $0.10 pe
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. In the beginning of the year, the company estimated its total overhead cost to be $325,000 and machine hou
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $271,700 and machine hou
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $310,000 and machine hou
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $325,000 and machine hou
- Cash Company has a predetermined overhead rate of $4 per machine hour. Last year the company incurred $112,400 of actual manufacturing overhead cost and the account was $4,200 over-applied. How many machine hours were used during the year? a. 16,800 mach
- Cash Company has a predetermined overhead rate of $4 per machine hour. Last year 'The company incurred $112,400 of actual manufacturing overhead cost and the account was $4,200 over-applied. How many machine hours were used during the year? a. 16,800 mac
- Manufacturing company has a standard costing system based on machine hours (MHs) What is the predetermined overhead rate to the nearest cent? (Show work) The following data pertain to operations for
- Factory maintenance costs are estimated for Bing Company based on the level of machine hours used. If total monthly fixed costs are $150,000, variable costs per machine hour are $8, and 15,000 machine
- Job 593 was recently completed. The following data have been recorded on its job cost sheet. T the Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead
- Smith Company expected to incur $10,000 in manufacturing overhead costs and use 4,000 machine hours for the year. Actual manufacturing overhead was $9,700 and the company used $4,250 machine hours. a. Calculate the predetermined overhead allocation rate
- Suppose budgeted production for EG Company is estimated to require 8,000 machine hours per year and practical capacity is 10,000 machine hours per year. Estimated manufacturing overhead cost for the y
- Renteria Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $306,300 for the year, and machine usage is estimated at 125,200 hours. For the year, $327,350 of overhead costs are incurred
- Gell Corporation manufactures computers. Assume that Gell: allocates manufacturing overhead based on machine hours. estimated 10,000 machine hours and $87,000 of manufacturing overhead costs. The predetermined overhead rate is $8.70 per machine hour. actu
- With 4,000 machine-hours in a month as an activity level, Brant Corporation's total variable production engineering cost is $154,200 and its total fixed production engineering cost is $129,000. What w
- Newton Corporation uses a job-order costing system and allocates manufacturing overhead at a rate of $25 per machine hour. During the period, the company used 600 machine hours and actually incurred manufacturing overhead costs of $14,500. a. Prepare a s
- Renteria Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $305,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine-hours. At the beginning of the year, the company estimated its total overhead cost to be $269,800 and machine hours to be 14,200. Actual manufacturing overhead and mach
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $296,000 and machine hours to be 14,800. Actual manufacturing overhead and mach
- Actual manufacturing overhead cost $410,000 Estimated manufacturing overhead cost $400,000 Estimated direct labor cost $180,000 Estimated direct labor hours 50,000 Actual direct labor hours 55,000 Estimated machine hours 80,000 Actual m
- Estimated machine hours used to set the predetermined overhead rate were 68,000, while actual hours were 64,000 for the period. The estimated (budgeted) overhead was $142,800. Assuming the company used a predetermined overhead rate, how much overhead was
- Sholette Manufacturing Corporation has a standard cost system in which it applies manufacturing overhead to products on the basis of standard machine-hours (MHs) at $7.00 per MH. During the month, the actual total variable manufacturing overhead was $42,2
- Sholette Manufacturing Corporation has a standard cost system in which it applies manufacturing overhead to products on the basis of standard machine hours (MHs) at $7 per MH. During the month, the actual total variable manufacturing overhead was $42,250
- Dearden Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $144,000,
- Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity Level 2500 Machine Hours Variable Overhead Cost: Supplies 12,250 Indirect Labor 22,000 Fixed Ove
- Cambridge Manufacturing Company applies manufacturing overhead on the basis of machine hours. At the beginning of the year, the company estimated its total overhead cost to be $300,200 and machine hou
- Consider the following production and cost data for two products, L and C: Product L Product C Contribution margin per unit $35 $40 Machine hours needed per unit 7 hours 5 hours The company can only perform 14,700 machine hours each period, due to limite
- Actual machine hours 970 Standard machine hours allowed 1,000 Denominator activity (machine hours) 1,210 Actual fixed overhead costs $10,360 Budgeted fixed overhead costs $10,890 Predetermined overhea
- Ikered Company applies manufacturing overhead to jobs on the basis of machine-hours used. Overhead costs are expected to total $ 300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred a
- Quintric Ltd. incurred actual total manufacturing costs of $202,000 and 8,000 total machine hours during the year. Determine the amount of under-applied or over-applied manufacturing overhead for the period and prepare a journal entry to close any balance
- Manufacturing overhead costs totaling $5,000,000 are expected for this coming year. The company also expects to use 50,000 direct labor hours and 20,000 machine hours. Required: a. Calculate the plantwide predetermined overhead rate using direct labor hou
- Acitelli Corporation, which applies manufacturing overhead on the basis of machine hours, has provided the following data for its most recent year of operations. Estimated manufacturing overhead $224,550 Estimated machine hours 4,500 Actual manufacturing