Consider the following project. Calculate the expected activity times for all the activities.

Question:

Consider the following project.

Activity Predecessors a m b
A Start 2 5 14
B Start 3 5 13
C A 3 8 13
D C 1 4 7
E B, C 6 9 18
F B 6 7 14
G D, E 7 10 19
H E, F 4 6 14
I F 3 4 17

Calculate the expected activity times for all the activities.

PERT Expected Time:

PERT expected time is defined as the expected average time taken by each activity to complete. It is calculated by taking three-time estimates of every activity. With the help of the expected time, the project manager can determine the project's completion time.

Answer and Explanation:

Become a Study.com member to unlock this answer!

View this answer

The formula for calculating expected time is:

{eq}Expected\;Time\left( {{t_e}} \right) = \dfrac{{a + 4 \times m + b}}{6} {/eq}

Where,

(a) stands...

See full answer below.


Learn more about this topic:

Loading...
PERT Analysis & Project Completion

from

Chapter 6 / Lesson 5
53K

Learn about PERT analysis, which is used to estimate the time it will take to complete a project. Explore the PERT formula and types of time, and look at examples.