Consider the following project. Calculate the expected activity times for all the activities.
Question:
Consider the following project.
| Activity | Predecessors | a | m | b |
|---|---|---|---|---|
| A | Start | 2 | 5 | 14 |
| B | Start | 3 | 5 | 13 |
| C | A | 3 | 8 | 13 |
| D | C | 1 | 4 | 7 |
| E | B, C | 6 | 9 | 18 |
| F | B | 6 | 7 | 14 |
| G | D, E | 7 | 10 | 19 |
| H | E, F | 4 | 6 | 14 |
| I | F | 3 | 4 | 17 |
Calculate the expected activity times for all the activities.
PERT Expected Time:
PERT expected time is defined as the expected average time taken by each activity to complete. It is calculated by taking three-time estimates of every activity. With the help of the expected time, the project manager can determine the project's completion time.
Answer and Explanation:
Become a Study.com member to unlock this answer! Create your account
View this answerThe formula for calculating expected time is:
{eq}Expected\;Time\left( {{t_e}} \right) = \dfrac{{a + 4 \times m + b}}{6} {/eq}
Where,
(a) stands...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:
from
Chapter 6 / Lesson 5Learn about PERT analysis, which is used to estimate the time it will take to complete a project. Explore the PERT formula and types of time, and look at examples.
Related to this Question
- Consider the following table of activities, completion times and predecessors. 1) Determine the expected completion time of each activity 2) Draw the network diagram for this project
- Consider the following table of activities, completion times and predecessors. 1) Determine the expected completion time of this project, in days. 2) Which activities are on the critical path? 3) Which activities have slack? How much slack these activitie
- The activities of a project are shown in the following table, with their precedence relations and the three time estimates. a. Find the expected time for activity F. b. What is the variance for activi
- Consider a project having the following ten activities a) What is the expected project completion time? b) What is the critical path? c) What is the most economical way and how much will it cost to r
- Consider a project with the following activity list. | Activity | Immediate | Predecessors | Estimated Duration (months) | A | - | 1 | B | A | 2 | C | B | 4 | D | B | 3 | E | B | 2 | F | C | 3
- Project Management Activity: 1. Calculate the "expected time" and "activity variance" for each activity. 2. Construct the network. 3. Use the "expected time" of each activity to identify the critical
- Consider the following project tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization you work for computes TE based on the standard beta distribut
- a. Draw a network for the project using the immediate predecessors. b. Calculate the expected activity times for all the activities.
- Consider a project having the following ten activities: Show the work on how to get the solutions : (a) What is the expected project completion time? (b) What is the critical path? (c) What is the
- Determine both the critical path in the expected project duration. The numbers on the arrows represent expected activity times.
- The activity time estimates used to build a project network are derived from _____.
- Given the following details of activities and time estimated in days a) What are the critical path activities? b) What is the expected time to complete the project? c) What is the probability that
- Use the following information to determine the probability of this project finishing within 34 weeks of its scheduled completion date. Assume activities A - B - D - F - G are the project's critical pa
- Use the data given in the following table and relationships between activities shown in the Activity on Node(AON) network. Find the project duration(earliest completion time of the project) a) 21 b)
- Given the following information, you are to determine the following: Project network. Early, late and slack activity times. Project duration. Critical path.
- Consider the project activities given below:Where the appropriate managers have made estimates of the optimistic, most likely, and pessimistic times (in days) for completion of the activities. a. Draw
- Using the following project information, calculate the expected time for each of the project activities (Round your answer to 2 decimal places, the tolerance is +/-0.01)
- The following table shows the three time estimates for the activities of a given Project. a. What is the Project expected completion time ? (Round your answer to three decimal places) b. Find the P
- In the following table the activities with their precedence sequence and expected time(days) are listed for a project a) Determine the activities on the critical path b) determine the project length
- Use the following information to determine the probability of the project finishing within 34 weeks of its scheduled completion date. Assume activities A-B-C-F-G are on the project's critical path. a
- Consider a project having the following seven activities: (a) What is the expected project completion time? (b) What is the most economical way and how much will it cost to reduce the completion ti
- Consider a project having the following seven activities: (a) What is the expected project completion time? (b) What is the most economical way and how much will it cost to reduce the completion t
- Consider the information given below. Calculate the amount of float for Activity E. | Activity | Predecessor | Duration (weeks) | Project Kickoff | | 0 | Prototype Development (D) | Start | 4 | Preliminary Design Activities (A) | Start | 6 | Preliminar
- Consider the network described in the table below. 1. Calculate the expected duration and variance of each activity.
- A project consist of the following activities as shown in the table. What is the amount of slack associated with Activity C? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7 | F | E |
- A project consist of the following activities as shown in the table. What is the earliest finish time for Activity D? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7 | F | E | 13
- The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATEPREDECESSOR a m b A --- 1 2 6 B --- 1 2 3 C A 2 5 11 D A 1 2 12 E B 1 2 3 F C, D 1 3 5 G D, E 1 3
- Given below is a PERT project network diagram. Determine the critical activities. | Activity | Start | A | B | C | D | E | F | G | H | End | Time | 0 | 2.61 | 5.00 | 6.31 | 5.31 | 2.65 | 4.23 | 4.12 | 7.13 | 0
- Use the activity table below to determine the expected activity lengths and variances for each of the activities, using the beta distribution. Activity Time estimates: a, m, b (days) 1 3, 10, 20 2 3,
- A project consist of the following activities as shown in the table. What is the time to complete the entire project? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7 | F | E | 13
- a) Based on the activity time estimates, the expected times and varlance for each of the activities are (round your responoe to two decimal place) b) The expected completion time of the critical pat
- Consider the following work breakdown structure: What is the estimated slack time for activity E? a. 0 weeks b. 3 weeks c. 12 weeks d. 9 weeks e. 11 weeks
- a. Develop the earliest and latest start and finish times and the slack time for all the activities. b. Calculate the variance and standard deviation of the project completion time.
- Consider the following information: A. calculate the Expected return to each project: B. rank these projects in terms of attractiveness from a risk- averse perspective: C. assess how your answers c
- Given the following information, you are to determine the following: Project network. Early, late and slack activity times. Project duration. Critical path \\ |Task |Predecessor |Duration |A |Non
- In the following table, the activities with their precedence, sequence, and expected time(days) are listed for a project a) In how many days will the project be completed? b) Which activities are on
- Given below is a PERT project network diagram. Determine the project completion time. | Activity | Start | A | B | C | D | E | F | G | H | End | Time | 0 | 2.61 | 5.00 | 6.31 | 5.31 | 2.65 | 4.23 | 4.12 | 7.13 | 0
- The following represents a project that should be scheduled using CPM: a. What is the critical path? B-E-G-H A-D-F-H A-C-F-H A-D-G-H b. What is the expected project completion time?
- Consider the following project network and activity times (in weeks): Activity-Time: A-5, B-3, C-7, D-6, E-7, F-3, G-10, H-8 a) identify the critical path b) how much time will be needed to complete t
- A network consists of the activities in the following list. a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. c. What is project completion time? d. Identif
- A renovation project requires six activities. The following table provides the estimates for the optimistic, most likely, and pessimistic times for each of the activities. The expected activity times
- The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project. a. Draw a project network and determine the earliest and latest activity times, the e
- Consider the information given below. Calculate the critical path of the project. | Activity | Predecessor | Duration (weeks) | Project Kickoff | | 0 | Prototype Development (D) | Start | 4 | Preliminary Design Activities (A) | Start | 6 | Preliminary
- Assume that the activities stated below have the following costs to shorten: A, $300/week; B, $100/week; C, $200/week; E, $100/week; and F, $400/week. Assume also that you can crash an activity down
- In Project schedule activities, where do these activities come from?
- Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors A None B A C A D C E D F B, E a. Only activities B or C cou
- A company decides to plan a project, with activities, precedence and random duration statistics in the following
- Consider the following information: Project, Boom (50%), Recession (50%); A, $40, -$10; B, -$10, $40; C, $50, $50; D, $40, -$40. a. Calculate the expected return to each project; show your work. b. Ra
- The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent. [TABLE] a) Calculate the expected time and variance
- Consider the following breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E
- The formula to calculate the expected time or the weighted average of the tasks, using the three time estimates for each task, is [{Blank}] . A) (a + 4m + b) B) (a - 4m - b)/6 C) (a - 4m - b) D) 6(a + 4m + b) E) (a + 4m + b)/6
- A company decides to plan a project, with activities, precedence and random duration statistics given in the following table:
- Consider the following breakdown structure. What is the estimated expected mean time for project completion?Time Estimates days Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C A D 3
- A project consist of the following activities as shown in the table. What is the latest start time for Activity B? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7 | F | E | 13
- Based on the activity time estimates, the expected times and variance for each of the activities are: The expected completion time of the critical path = weeks The expected completion time of the path
- The following represents a project that should be scheduled using CPM: 1. What is the critical path? a. B-E-G-H b. A-D-F-H c. A-C-F-H d. A-D-G-H 2. What is the expected project completion time? 3. Wha
- The forward pass in project network calculations determines all of the following except: a. duration of the project b. earliest time an activity can begin c. the critical path d. earliest time an activity can finish e. how soon the project can finish
- A project consist of the following activities as shown in the table. The critical path for this project consists of what activities? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7
- The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H A-D-F-H B-E-G-H A-C-F-H c. What is the expected project completion time? (Round your
- A given project's duration along its critical path is 33 days and the total slack for one of the activities is 1 day. The planned finish time for the project is:
- Consider the following work breakdown structure What is the probability that for this project will be completed within 160 days Time Estimates days Activity Precedes Optimistic Most Likely Pessimistic
- The following activities are part of a project to be scheduled using CPM: | Activity | Immediate Predecessor | Time (weeks) | A | - | 8 | B | A | 3 | C | A | 7 | D | C | 3 | E | B,D | 4 | F | D
- In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) A - 7 B A 2 C A 4 D B 5 E B
- Consider the following information : a) calculate the expected return of each project b) Rank these projects in terms of attractiveness from a risk-averse perspective c) Assess how your answers chang
- The below table shows the activities, three estimates of project duration, and the precedence relationships for the project. a. Construct an activity on node (AON) network for this project. b. Calcula
- Given the following activities, what's the shortest time this project can be done in?
- Activity, a, m, b, Predecessor(s); A, 8, 10, 13, -; B, 6, 10, 16, -; C, 8, 9, 13, A; D, 6, 8, 14, B. a) Based on the activity time estimates, the expected times and variance for each of the activities
- The following represents a project that should be scheduled using CPM: 1. What is the critical path? a. A-D-F-H b. B-E-G-H c. A-D-G-H d. A-C-F-H 2. What is the expected project completion time?
- The activity table below corresponds to a project with critical path 2 ? 3 ? 9 ? 10 ? 13 . Find the mean length and variance of each task on the critical path.
- A project consist of the following activities as shown in the table. What is the earliest start time for Activity F? | Activity | Activity Predecessor | Time (weeks) | A | --- | 3 | B | A | 7 | C | --- | 6 | D | A, B | 11 | E | B | 7 | F | E | 13
- The following represents a project that should be scheduled using CPM: What is the critical path? a. A-C-F-H b. A-D-F-H c. A-D-G-H d. B-E-G-H What is the expected project completion time? Project Comp
- Using the provided data values for minimum expected activity duration and maximum expected activity duration, use Excel to provide a PERT analysis of the project given in Table 1. Include all calculat
- You are the Project Manager for the development of a new product. Details regarding the activities, precedence relationships and time estimates are provided in the table below: [TABLE] a. Determine the expected duration and variance for each activity. b.
- A student wants to schedule a project using CPM. She has determined the following activities, precedence relationships and time estimates in days for the project. | Activity | Immediate Predecessors
- Consider the following investment projects a) Compute the IRR for each project b) determine the range of MARR where project 2 would be preferred over project 1
- Given the following project network and activity durations, answer the questions below. A. Find the early and late start activity and finish times. B. What is the Critical path? C. Can activity B be
- Schedule the following activities using CPM: What is the critical path? a. A-B-D-F-G-H b. A-C-E-H c. A-C-D-F-G d. A-B-D-E-H How many weeks will it take to complete the project?
- The following represents a project that should be scheduled using CPM with 3 time estimates. What is the project will exceed 30 weeks? a. 15.39% b. 34.16% c. 27.67% d. 28.67%
- In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) A -5 B A 2 C A 4 D B 5 E B 5 F C 5
- Consider a project having the following six activities: *Shortest possible time for task 1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and lates
- Consider the following work breakdown structure: Activity_Precedes_Optimistic time estimate (days)_Most likely time estimate (days)_Pessimistic time estimate (days) Start_A, B, C_-_-_- A_D_38_50_62
- The following represents a project with known activity times. All times are in weeks. 1. Using the above data, what it the minimum possible time required for completing this project? a. 8 b. 14 c. 25
- A company decides to plan a project, with activities, precedence and deterministic durations given in the following table: 1.1) What method should be used? Using only one pseudo-activity, draw the
- Consider the following network diagram. Calculate the slack for task E :
- Consider the table below. Develop a forecast for the next period (period 6) using a 4-period moving average. | Period | Demand | 1 | 19 | 2 | 20 | 3 | 18 | 4 | 19 | 5 | 17
- Here is a list of activity times for a project as well as crashing for its activities. Determine which activity should be crashed and the total cost of crashing if the goal is to shorten the project b
- Consider the following project information: What is the standard deviation of the critical path's time? ANSWERS: - cannot be determined - 1.92 - 3.69 - 1.09 - 1.19
- The progress data after 21 days of a certain project are given in the table below. Draw a Gantt chart showing the timing of planned project activities.
- Using the information in the table below, create an AON network activity diagram. Calculate each activity TE (rounding to the nearest integer); the total duration of the project; its early start, earl
- The following represents a project that should be scheduled using CPM: 1: Draw the network. 2: What is the critical path? 3: what is the expected project completion time?
- The following table represents a plan for a project. a. Indicate the critical path. b. What is the expected completion time (in days) for the project?
- Consider the following work breakdown structure: Duration Estimates Days Activity Precedes Optimistic Most Likely Pessimistic Start U, V U W 35 50 65 V W, X 28 40 52 W Z 26 35 44 X Y 28 40 52 Y Z 26
- Given the project information in the table below, draw a fully analyzed network diagram for the project showing all activity times. Develop a project schedule table, define the critical path, and find
- Using the project information in the table below, draw a fully analyzed network diagram for the project showing all activity times. Develop a project schedule table, define the critical path, and find
- The following activities are part of a project to be scheduled using CPM: What is the critical path? a. A-C-D-E-G b. A-C-D-F-G c. A-B-E-G How many weeks will it take the complete the project? Number o
- Given the activity times and precedence requirements for a project shown in the table, what is the earliest time to complete the project? (a) 27 days, (b) 28 days, (c) 30 days, (d) 33 days
- Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 0.5 2 3.5 B 1 3 5 C 4 6 8 D 4 5.5 10 E 3 7
- Consider the following two mutually exclusive projects. Whichever project you choose, if any, you require a return of 14% on your investment. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2
- Given the project information in the table below, determine the Project network Critical path(s) Project duration Project cost Activity Predecessors Duration (Days) Normal Cost, $ A - 5 100 B A 7 140