Compute the IRR static for Project I. The appropriate cost of capital is 8 percent. Project l...
Question:
Compute the IRR static for Project I. The appropriate cost of capital is 8 percent.
Project l
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow | 2,100 | 920 | 810 | 850 | 520 |
Should the project be accepted or rejected?
Internal rate of return:
The internal rate of return (IRR) is a method under capital budgeting used to determine if a project is feasible or not. This method estimates the discount rate at which the project will have a zero NPV. IRR is based on the time value of money concept and it discounts the future cash flows to their present worth which should be equivalent to the cost. A project evaluated under this method is considered acceptable if the IRR > cost of capital.
Answer and Explanation: 1
Become a Study.com member to unlock this answer! Create your account
View this answerWe calculate IRR using the method of interpolation;
This requires us to use the trial and error process and choose two discount rates that yield a...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:

from
Chapter 14 / Lesson 7Discover what the internal rate of return is. Learn its importance and uses. Review its formula and learn how to calculate it through the given examples.
Related to this Question
- 1. Compute the PI static for your firm's new project if the appropriate cost of capital is 9 percent. Time 0 1 2 3 4 5 6 Cash Flow -680 80 560 760 760 360 760 2. Should the project be accepted or rejected?
- Compute the IRR for Project F. The appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Should the project be accepted or rejected?
- a) Compute the MIRR statistic for Project I if the appropriate cost of capital is 11 percent. b) Should the project be accepted or rejected?
- Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent. Project I: Time: 0 1 2 3 4 Cash flow -$11,000 $5,330 $4,180 $1,520 $2,000
- Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. Should the project be accepted or rejected? | Time| 0| 1| 2| 3 |4 |5 |Cash flow| -$2,900| $920| $2,430| -$71
- Compute the MIRR statistic for Project I if the appropriate cost of capital is 12 per cent. Should the project be accepted or rejected?
- 1. Compute the NPV statistic for Project Y if the appropriate cost of capital is 13%. Time 0 1 2 3 4 Cash flow -$9,100 $3,570 $4,400 $1,740 $520 2. Should the project be accepted or rejected?
- Compute the NPV statistic for Project Y if the appropriate cost of capital is 13%. Should the project be accepted or rejected? Time: 0 1 2 3 4 Cash flow -$8,800 $3,510 $4,340 $1,680 $460
- Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11 percent. Time 0 1 2 3 4 5 Cash flow -78 -78 0 113 88 63 a. 51, accept b. 29.71,
- Compute the Payback statistic for Project X and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 11% and the maximum allowable payback is 3 years. Time 0 1 2 3 4 5 Cash fl
- Compute the MIRR statistic for Project I if the appropriate cost of capital is 11 percent. (Do no intermediate calculations. Round your final answer to 2 decimal places.) Project 1 Time: 0 1 2 3
- Compute the NPV statistic for Project Y if the appropriate cost of capital is 10 percent. Project Y Time: 0 1 2 3 4 Cash flow $8,500 $3,730 $4,560 $1,900 $680
- A firm with a cost of capital of 13 percent is evaluating three capital projects. The internal rates of return are as follows: Project 1 - 12% Project 2 - 15% Project 3 - 13% The firm should __________. A) accept Project 3, and reject Projects 1 and 2. B
- You estimate that a project will cost $27,700 and will provide cash inflows of $11,800 in year 1 and $24,600 in year 3. Based on the profitability index rule, should the project be accepted if the discount rate is 14 percent? Why or why not?
- Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years Project C Time: 0 1 2 3 4 5
- Project B Time (Years) 0 1 2 3 4 5 Cash Flow ($12,700) $3,520 $4,520 $1,860 $0 $1,340. Required: 1. Compute the payback statistic for Project B if the appropriate cost of capital is 11 percent and the
- Project A costs $10,000 and has annual cash flows of $2,900 for six years. The discount rate is 5%. Calculate the profitability index of the project. Should the firm accept the project?
- The IRR of normal Project X is greater than the IRR of normal Project Y, and both IRRs are greater than zero. Also, the NPV of X is greater than the NPV of Y at the cost of capital. If the two projects are mutually exclusive, Project X should definitely b
- a. Calculate the payback period for projects A and B. b. If only one can be chosen and the required rate of return is 12%, which should be accepted? Why? (use NPV as capital budgeting method) c. Calculate the approximate IRR for projects A and B. d. Calcu
- Compute the payback statistic for Project A If the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to
- Compute the net present value for each project. Rank the projects based on the computed value. Which project do you recommend?
- For the project shown in the following table, calculate the internal rate of return (IRR). Also indicate the maximum cost of capital that the firm could have and still find the IRR acceptable. |Cash
- Project L costs $45,168.92, its expected cash inflows are $9,000 per year for 10 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
- A company that is using the internal rate of return (IRR) to evaluate projects, should accept the project if the IRR: a. is greater than the project's net present value. b. is less than the project's net present value. c. is greater than the cost of capit
- Compute the NPV for Project K if the appropriate cost of capital is 6 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer
- If only one project can be chosen and if the discount rate is 12%, which project should be accepted? Why? (Use NPV for the analysis.)
- 1. Consider the following project's cash flows: Assume that the project's IRR is 10%. a) Find the value of X. b) Is this project acceptable at MARR = 8%? 2. You are considering a luxury apartment b
- Compute the annual rate of return for each project. Rank the projects based on the computed value. Which project do you recommend?
- An all-equity firm is considering the following projects: Project Beta IRR W 0.65 9.5% X 0.74 10.7% Y 1.33 14.2% Z 1.44 17.3% The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. If the firm's overall cost of capital wer
- Using a cost of capital of 14% calculate the net present value for the project shown in the following table and indicate whether it is acceptable Initial Investment (CFo) $62,500 Year (t) Cash Flows(
- An all-equity firm is considering the following projects: Project Beta IRR W 0.65 9.5% X 0.74 10.7% Y 1.33 14.2% Z 1.44 17.3% The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. If the firm's overall cost of capital w
- Suppose you are considering two projects, A and B, that each has a required rate of return of 10%. Both projects cost $5,000 and have a net present value of $150. Project A has an IRR of 16% and project B has an IRR of 15%. What is the crossover rate for
- You have just completed the analysis of a capital budgeting proposal and have concluded that the NPV = -5000. (You used a 12% discount rate) Before you decide that the project is not worthwhile, you note that you assumed that all the $400000 in financing
- When making screening decisions using the net present value method, a project is acceptable if: a. the NPV is greater than the hurdle rate. b. the NPV is greater than the IRR. c. the NPV is positive. d. the NPV is negative.
- Select the incorrect statement concerning the internal rate of return (IRR) method of evaluating capital projects. (a) The higher the IRR, the better (b) A project whose IRR is less than the cost of capital should be rejected (c) If a project has a positi
- For the cash flow of a project shown in the table below, decide whether to accept or reject the project. Assume MARR = 15% per year Questions: 1. Decide the project using IRR function in MS Excel.
- An all-equity firm is considering the following projects: Project Beta IRR W 0.65 9.5% X 0.74 10.7% Y 1.33 14.2% Z 1.44 17.3% The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. If the firm's overall cost of capital
- Assume that you have an after-tax cost of capital of 10 percent. Compute the net present value of each of the five projects listed in the following table. After-Tax Cash Flow, End of Year Project 0 1 2 3 A $(10,000) $4,000 $4,000 $4,000 B $(10,000) $6,00
- What is the net present value of the project if the appropriate discount rate is 20%?
- What is the net present value of the project if the appropriate discount rate is 12%?
- Two projects, Project A and Project B, are available, each costing $500,000. The discount rate is 10%. Considering the cash flows given below, which project would be more profitable using the net present value (NPV) method? | Year | Project A | Project B
- Compute the net present value of the project taking all cash flows into consideration. Based on the value, should the company proceed with the project?
- The following estimates have been prepared for a project under consideration: Fixed costs: $15,000 Depreciation: $9,000 Price: $4
- Project L costs $55,000, its expected cash inflows ere $11,000 per year for 8 years, end its WACC is 9%. What is the project's MIRR? (Do not round your intermediate calculations.)
- A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$30,000 $10,000 $10,000 $10,000 $10,000 $10,000 Project N -$90,000 $28,000 $28,000 $2
- A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$30,000 $10,000 $10,000 $10,000 $10,000 $10,000 Project N -$90,000 $28,000 $28,000 $28,0
- A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$30,000 $10,000 $10,000 $10,000 $10,000 $10,000 Project N -$90,000 $28,000 $28,000
- A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$30,000 $10,000 $10,000 $10,000 $10,000 $10,000 Project N -$90,000 $28,000 $28,000 $28,
- If the net present value of a project equals zero a. the project should be considered. b. the project should not be considered. c. then someone made an error in the calculation d. then a balanced scorecard should be adopted to compensate
- Complete the below table: ||A project will cost $1.0 million. The company uses a 10% discount rate as a threshold for accepting capital projects. It is expected to have a 5 year life and returns (net of all costs and taxes) the following: 2015 Spring2 |
- Project L costs $44,964.46, it's expected cash inflows are $10,000 per year for 9 years, and its WACC is 10%. What is the project's IRR?
- A five-year project has a projected net cash flow of $15,000, $25,000, $30,000, $35,000, and $20,000 in the next five years. It will cost $80,000 to implement the project. If the required rate of return is 20%, determine the NPV and indicate if you would
- Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 -$20,200 -$20,200 1 $8,900 $10,200 2 $9,200 $7,850 3 $8,850 $8,750 A. Calculate the IRR for each project. B. What is the crossover rate for these two projects? C. W
- Project K costs $44,887.46, its expected cash inflows are $10,000 per year for 9 years, and its WACC is 10%. What is the project's IRR?
- Project L costs $60,000, its expected cash inflows are $11,000 per year for 7 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places.
- Determine the FW of the following engineering project when the MARR is 12% per year. Is the project acceptable? Proposal A Investment cost $11,000 Expected life 6 year Market (salvage) value* -$800 A
- Investment projects. What is each project NPV if the cost capital is 10 percent? 5 percent? 15 percent? |Year |Project A |Project B |0 |-$1,500,000 |-$1,500,000 |1 |$500,000 |$2,000,000 |2 |$1,00
- Jella Cosmetics is considering a project that costs $750,000 and is expected to last for 9 years and produce future cash flows of $180,000 per year. If the appropriate discount rate for this project is 17 percent, what is the project's IRR?
- Charlie has a project for which he had determined a present value of $56,740. He now has to calculate the IRR for the project, but unfortunately he has lost complete information about the cash flows. He knows only that the project has a five-year service
- An all-equity firm is considering the following projects: Project Beta IRR W 0.65 9.5% X 0.74 10.7% Y 1.33 14.2% Z 1.44 17.3% The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. If the firm's overall cost of capital we
- A company that is using the internal rate of return (IRR) to evaluate projects should accept a project if the IRR: a. is greater than the project's net present value. b. equates the present value of the project's cash inflows with the present value of the
- Select the incorrect statement concerning the internal rate of return (IRR) method of evaluating capital projects. A. A project whose IRR is less than the cost of capital should be rejected. B. The higher the IRR the better. C. The internal rate of ret
- A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$30,000 $10,000 $10,000 $10,000 $10,000 $10,000 Project N -$90,000 $28,000 $28
- A project has estimated annual cash flows of $95,000 for 4 years and is estimated to cost $260,000. Assume a minimum acceptable rate of return of 10%. Determine the net present value of the project.
- Compute the cash payback period for each project. Rank the projects based on the computed payback period. Which project do you recommend?
- Project L costs $44, 964.46, its expected cash flows are $10,000 per year for 9 years, and its WACC is 10%. What is the project's IRR?
- If the net present value of an investment project is positive, then the project is [{Blank}]. If the net present value of an investment project is negative, then the project is [{Blank}]. A. desirable; undesirable B. ignored; accepted C. unacceptable;
- Consider a project with cash flows: Year 0 1 2 3 4 5 P -$19 $10 $5 $3 $5 $10 Compute the profitability index based on a 10% cost of capital and compute the payback time.
- Two projects, Project A and Project B, are available, each costing $500,000. The discount rate is 10%. Considering the cash flows given below, which project would be more profitable using the undiscounted payback period method? | Year | Project A | Proje
- Crispen Corporation can invest in a project that costs $400,000. The project is expected to have an after-tax return of $250,000 in each of years 1 and 2. Crispen normally uses a 10 percent discount rate to evaluate projects but feels it should use 12 per
- The internal rate of return is 12.10%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)
- Calculate the project cash flow generated for Project A and Project B using the NPV method. . Which project would you select, and why? . Which project would you select under the payback method? The di
- Project L costs $35,000, its expected cash inflows are $8,000 per year for 7 years, and its WACC is 12%. What is the project's NPV? (Round your answer to the nearest cent. Do not round your intermedia
- Project L costs $35,000, its expected cash inflows are $9,000 per year for 7 years, and its WACC is 13%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediat
- Project Health One (H1) has a cost of $76,543, it expected net cash flows are $20,000 per year for 6 years, and its cost of capital is 10%. Calculate the project's NPV.
- A project is expected to produce cash flows of $48,000, $39,000, and $15,000 over the next three years, respectively. After three years, the project will be worthless. What is the present value of this project if the applicable discount rate is 15.25 perc
- A project has estimated annual cash flows of $94,000 for four years and is estimated to cost $261,000. Assume a minimum acceptable rate of return of 10%. a. Determine the net present value of the project. b. Determine the present value index.
- What criteria determine whether a project is acceptable under the net present value method?
- A project that provides annual cash flows of $17,100 for nine years costs $77,000 today. a. What is the NPV for the project if the required return is 8 percent? (Round your answer to 2 decimal places. (e.g., 32.16)) b. At a required return of 8 percent, s
- We are evaluating a project that costs $756,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 6
- We are evaluating a project that costs $1,024,344, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected
- We are evaluating a project that costs $972,000, has a four-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at
- We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at
- For the project shown in the following table calculate the internal rate of return (IRR). (Round to two decimal places.) The project's IRR is _____ %. Initial investment $110,000 Year Cash flows 1 $4
- Compute the benefit-cost ratio and B-C criterion of the following project: Project cost P80,000 Gross income P25,000 per year Opening cost P6,000 per year Salvage value 0 Life of project 10 years Rate of interest 12%
- If the net present value of a project equals zero: a. the project should be considered. b. the project should not be considered. c. then someone made an error in the calculation. d. then a balanced sc
- The following estimates have been prepared for a project under consideration: Fixed costs: $20,000 Depreciation: $10,000 Price: $2 Accounting break-even: 60,000 units Required: What must be the
- A project has estimated annual net cash flows of $54,000 and is estimated to cost $334,800. What is the payback period? (Round the answer to 2 decimal places.)
- A project has estimated annual net cash flows of $60,000 and is estimated to cost $396,000. What is the payback period? (Round your answer to 2 decimal places.)
- Two projects, Project A and Project B, are available, each costing $500,000. The discount rate is 10%. Considering the cash flows given below, which project would be more profitable using the profitability index? | Year | Project A | Project B | 1 | 150,
- Winter wear is considering a 5-year project with an initial cost of $211,000. The project will induce cash inflows of $56,500 a year over the life of the project. What is the net present value if the required rate of return is 15.8 percent?
- Small Co. is considering the following project, whose cost of capital is 12% per annum: Year 0 1 2 3 Cash flows of the project (2,000) 1,000 800 700 Calculate the NPV of the project.
- A project has estimated annual net cash flows of $8,000 for five years and is estimated to cost $28,000. Assume a minimum acceptable rate of return of 12%. Determine (1) the net present value of the project and (2) the present value index.
- If a company's required minimum rate of return is 10%, and in using the net present value method, a project's net present value is zero, this indicates that the: A) project's rate of return exceeds 10%. B) project's rate of return is less than the minim
- Compute the net present value of each project. Company D is considering two different, mutually exclusive capital expenditure proposals. (a) Project A will cost $395,000, has an expected useful life of 10 years, a salvage value of zero, and is expected t
- A project has estimated annual net cash flows of $96,200 for four years and is estimated to cost $315,500. Assume a minimum acceptable rate of return of 10%. Determine (1) the net present value of the project and (2) the present value index.
- At a discount rate of 4%, a project returns a positive NPV of 5,300 pounds. At 8%, it returns a negative NPV of 4,800 pounds. To be nearest whole%, what would the IRR of the project be?
- Project L costs $55,000, its expected cash inflows are $11,000 per year for 8 years, and its WACC is 9%. What is the project's MIRR?
- A project has a life of 10 years and no salvage value. Your firm uses a MARR of 8% to evaluate projects. The project has uncertain costs and revenue as shown in the table below: Initial Cost Probabil
- If a project costing $70,000 has a profitability index of 1 and the discount rate was 12%, then the present value of the net cash flows was: A. greater than $70,000 B. undeterminable C. $70,000 D. less than $70,000