A project has cash flows of $15,000, $10,000, and $5,000 in 1, 2, and 3 years, respectively. If...
Question:
A project has cash flows of $15,000, $10,000, and $5,000 in 1, 2, and 3 years, respectively. If the prevailing interest rate is 15%, would you buy the project if it costs $25,000?
Net Present Value:
The net present value is a capital budgeting technique that discounts the expected cash flow at the required rate of return to compute the current worth of the project.
Answer and Explanation: 1
Become a Study.com member to unlock this answer! Create your account
View this answerComputation of net present value
Year | PVF @ 15% | Cash Flow | Present Value |
---|---|---|---|
0 | 1.0000 | -$25,000 | -$25,... |
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:

from
Chapter 14 / Lesson 3The net present value (NPV) method considered future cash flows to evaluate the value of capital projects—those that increase or decrease an enterprise's value. Learn how this method is calculated and guides budget decisions.
Related to this Question
- If a project has the following cash flows: Year 0 = (500) Year 1 = 140.00 Year 2 = 200.00 Year 3 = 290.00 What is the project's NPV if the interest rate is $6%?
- A project has the following cash flows. 0 1 2 3 ($500) $120 $200 $310 What is the project's NPV if the interest rate is 6%?
- A project has the following cash flows: What is the project NPV if the interest rate is 6%?
- A project has the following cash flows: Year 0 1 2 3 Cashflow ($500) $100 $200 $290 What is the project's NPV if the interest rate is $6%?
- If: Acquisition Cost = $10000.00 Annual Cash Flow = $4092.16 Project length 3 years The hurdle rate is 8% What is IRR? 10% 2.4% 8% 11% 40.9%
- Find the net present value of a project that has cash flows of-$12,000 in Year 1, +$5,000 in Years 2 and 3, -$2,000 in Year 4, and +$6,000 in Years 5 and 6. Use an interest rate of 12%. Find the
- A project is estimated to cost $108,490 and provide annual net cash flows of $38,000 for four years. Present value of an annuity of $1 at compound interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.4
- A project is estimated to cost $463,565 and provide annual net cash flows of $115,000 for nine years. Determine the internal rate of return for this project, using the Present Value of an Annuity of $1 at Compound Interest table shown below.
- Given the following cash flows for a capital project, calculate the IRR. Year 0 1 2 3 4 5 Cash Flows ($50,467) $12,746 $14,426 $21,548 $8,580 $4,959 Options: a. 8.41%. b. 8.05%. c. 8.79%. d. 7.9%.
- A project has cash flows of -$12,000 in Year 1, +$5000 in Years 2 and 3, -$2000 in Year 4, and +$6000 in Years 5 and 6. Use an interest rate of 12%. Find the interest rate that gives a net present val
- A project that provides annual cash flows of $17,600 for 9 years costs $82,000 today. 1. What is the NPV for the project if the required return is 8%? 2. What is the NPV for the project if the required return is 20%? 3. At what discount rate would you be
- What is the present value of the following cash flow stream at a rate of 4%? Years Cash flows 0 -$1,000 1 $2,450 2 $3,178 3 $4,400 a. $7,917 b. $8,333 c. $8,772 d. $8,703 e. $8,202
- A project that costs $4,900 to install will provide annual cash flows of $1,650 for each of the next 6 years. A. Calculate the NPV if the discount rate is 14%. B. Is this project worth pursuing? C. How high can the discount rate be before you would reject
- A proposed project will cost $684,805 and will provide returns of $150,000 in Year 1, $300,000 in Year 2, and $400,000 in Year 3. There will not be any cash flows associated with the project after Year 3. If taxes are ignored, what is the internal rate o
- A project that provides annual cash flows of $17,600 for nine years costs $82,000 today. a. What is the NPV for the project if the required return is 8 percent? b. What is the NPV for the project if the required return is 20 percent? c. At what discoun
- Calculate the Future Value of $1 in each of these 3 projects : Project Number of Periods ; Interest Rate ; A - 5 ,11%; B - 4, 7%; C - 3, 8%. Calculate the Present Value of each of the Projects below:
- ABC is reviewing a project that will cost $1,438. The project will produce cash flows of $446 at the end of each year for the first two years and $643 at the end of each year for the next two years. What is the profitability index? Assume the interest ra
- The interest rate that sets the present value of a project's cash inflows equal to the present value of the project's cost is called the _______________. a. present value b. discount rate c. internal rate of return d. payback period e. company cost o
- A project will cost $50,000 initially. The benefits at the end of the first year are estimated to be $10,000, increasing at a rate of 10% in each of the following years for 8 years. Using a 10% interest rate, the simple payback period is closest to a) 1
- A project that provides annual cash flows of $17,100 for nine years costs $77,000 today. a. What is the NPV for the project if the required return is 8 percent? (Round your answer to 2 decimal places. (e.g., 32.16)) b. At a required return of 8 percent, s
- You are considering a project which will provide cash inflows of $2,100, $4,000, and $5,500 per year over the next three years, respectively. What is the present value of these cash flows, given a 13 percent discount rate? A. $7,487.78. B. $8,050.00. C. $
- Cannonier, Inc., has identified an investment project with the following cash flows. Year Cash flow 1 $930 2 1,160 3 1,380 4 2,120 a. If the discount rate is 7 percent, what is the future value of these cash flows in Year 4? (Do not round intermediate cal
- You are considering a project with an initial cash outlay of 60,000 Lira and expected free cash flows of 20,000 Lira at the end of each year for 5 years. The required rate of return for this project is 12%. A. Calculate the project's payback period. B.
- A project costing P250,000 yields a yearly benefit of P80,000 for a period of 10 years with no salvage value at an interest rate of 6%. What is the benefit-cost ratio?
- What is the FV at the end of year 4 of the following project? (Assume r = 10%) Year 1: Cash Flow $8,000, Year 2: Cash Flow $9,000, Year 3: Cash Flow $10,000, Year 4: Cash Flow $20,000.
- An investment project provides cash flows of $595 per year for 5 years. What is the project payback period if the initial cost is $5,500. Annual cash inflow = $595 No. of years = 5 Initial cost = $5,500 a. 9.24 b. 0.11 c. 119.00 d. 0.54
- An investment project has annual cash inflows of $8,200, $8,600, $8,800, and $7,600, and a discount rate of 7 percent. What is the discounted payback period for these cash flows if the initial cost is $23,839?
- What is the present value of the following cash flow stream at a rate of 8%? Year Cash Flow 0 $0 1 $2,450 2 $3,175 3 $4,400
- A project has estimated annual cash flows of $95,000 for 4 years and is estimated to cost $260,000. Assume a minimum acceptable rate of return of 10%. Determine the net present value of the project.
- A project has estimated annual cash flows of $90,000 for three years and is estimated to cost $250,000. Assume a minimum acceptable rate of return of 10%. Using the following tables determine the (a) net present value of the project and (b) the present va
- A project's annual revenues will be $50,000 the first year and will decrease by $1,500 per year over its 20-year life. If the firm's interest rate is 12%, what is the project's present worth? (a) $30
- A project that costs $3,500 to install will provide annual cash flows of $1,050 for each of the next 6 years. Calculate the NPV if the discount rate is 15%. (Do not round intermediate calculations. Ro
- You are scheduled to receive an $800 cash flow in one year, a $950 cash flow in two years, and pay a $1,000 payment in three years. If interest rates are 8percent per year, what is the combined present value of these cash flows?
- What is the payback period for the following set of cash flows? Year Cash Flow 0 -$ 4,800 1 2,500 2 1,000 3 1,600 4 1,200 a. 2.76 years b. 2.81 years c. 3.11 years d. 2.83 years e. 2.95 years
- A project has estimated annual net cash flows of $15,000 for three years and is estimated to cost $40,000. Assume a minimum acceptable rate of return of 15%. Use the Present value of an Annuity of $1 at Compound Interest table below.
- An investment project has annual cash inflows of $5,200, $3,000, $4,300, and $3,500, for the next four years, respectively. The discount rate is 13 percent.
- A project has estimated annual cash flows of $94,000 for four years and is estimated to cost $261,000. Assume a minimum acceptable rate of return of 10%. a. Determine the net present value of the project. b. Determine the present value index.
- Huggins Co. has identified an investment project with the following cash flows: Year Cash Flow 1 $730 2 950 3 1,210 4 1,300 A. If the discount rate is 8 percent, what is the present value of these cash flows? B. What is the present value at 18 percent?
- A project has estimated annual net cash flows of $6,250 for two years and is estimated to cost $50,000. Assume a minimum acceptable rate of return of 12%. Use the Present Value of an Annuity of $1 in the Compound Interest table below. Present Value of an
- What is the value of the cash flows 5 years from today? Interest rate = 6.3%. Year Cash flow 1 $3,540 2 $4,655 3 $5,630 4 $6,910
- What is the payback period for the set of cash flows givenbelow? Year Cash Flow 0 - $5,500 1 $1,300 2 $1,500 3 $1,900 4 $1,400
- What is the present value of a perpetual stream of cash flows that pays $80,000 at the end of the one year and grows at a rate of 7% indefinitely? The rate of interest used to discount the cash flows is 9%. What is the present value of the growing perpetu
- You are considering a project with an initial eash outlay of $70,000 and expected free cash flows of $28,000 at the end of each year for 6 years The required rate of return for this project is 9 perce
- Compute the cash payback period for each project. Rank the projects based on the computed payback period. Which project do you recommend?
- Project ABC is under consideration. Annual cash flows equal $50,000 per year for 5 years. During the first three years, the required rate of return is 2 percent. The required rate of return for cash flows in the final two years is 10 percent. What is the
- A project is estimated to cost $248,400 and provide annual cash flows of $50,000 for eight years. Determine the internal rate of return for this project, using the following table.
- A proposed investment will provide cash flows of $50,000, $10,000, and $7,000 at the end of Years 1, 2, and 3, respectively. Using a discount rate of 20 percent, determine the present value of these cash flows.
- What is the payback period for the set of cash flows given below? Year Cash Flow 0 $-5,500 1 $1,300 2 $1,500 3 $1,900 4 $1,400
- Determine the value of "X" from the cash flows given in the table below at an interest rate of 8% for a break-even cash flow. Year 0 1 2 3 4 5 Cash flows -10,000 + X 699 700 800 900 900
- A proposed investment will provide cash flows of $30,000, $7,000 and $5,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 16%, determine the present value of these cash flows for Year 2.
- A proposed investment will provide cash flows of $30,000, $7,000 and $5,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 16%, determine the present value of these cash flows for Year 1.
- A proposed investment will provide cash flows of $30,000, $7,000 and $5,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 16%, determine the present value of these cash flows for Year 3.
- If a project costs $110,000 and is expected to return $24,000 annually, how long does it take to recover the initial investment? What would be the discounted payback period at i = 17%? Assume that the cash flows occur continuously throughout the year.
- Seaborn Co. has identified an investment project with the following cash flows. Year Cash Flow 1 $900 2 $1,050 3 $1,220 4 $1,130 (a) If the discount rate is 12 percent, what is the present value of these cash flows? (b) What is the present value at 17 pe
- Annual cash inflows that will arise from two competing investment projects are given below: Year Investment A Investment B 1 $1,000 $4,000 2 $2,000 $3,000 3 $3,000 $2,000 4 $4,000 $1,000 Total $10,000 $10,000 The discount rate is 9%. Required: Compute t
- Suppose a project has a $2,000,000 net investment and net cash flows (NCFs) of $700,000 annually for 7 years. If the investor's required rate of return is 10%, what is the NPV of this project?
- What is the modified internal rate of return of a project with a three-year duration, cost of capital of 10%, initial outlay of $10,000, and cash inflows of $5,000 per year between years 1 through 3?
- Given the cash flows below what would be the future worth (FW) of this project if MARR = 12%? Year Cash Flow 0 ($4,000) 1 $500 2 $2,000 3 $3,000 4 $4,000 5 $1,250
- Bower Co. is reviewing a capital investment of $50,000. This project's projected cash flows over a five-year period are estimated at $20,000 each year. Calculate the payback period.
- Bower Co. is reviewing a capital investment of $50,000. This project's projected cash flows over a five-year period are estimated at $20,000 each year. Required: (a) Calculate the payback period. (
- A project has estimated annual net cash flows of $27,000 for eight years and is estimated to cost $127,216. Assume a minimum acceptable rate of return of 15%. Use the Present Value of an Annuity of $1
- What is the value in year 4 of a $630 cash flow made in year 8 if interest rates are 8 percent?
- What is the value in year 9 of a $1,400 cash flow made in year 4 if interest rates are 10 percent?
- What is the internal rate of return of a project with an initial outlay of $9,000 resulting in a free cash flow of $1,086 at the end of the year for the next 12 years?
- What is the annualized discount rate % and your annualized investment rate % on a Treasury bill that you purchase for $9,940 that will mature in 91 days for $10,000?
- Project yield annual net cash inflows are $10,500 for the next five years; interest rate of 16.5%, and the initial investment of $33,000. Calculate the net present value of the cash flows and the IRR for the project. Explain the concept of Net Present Val
- You purchase a car at $22,000. The interest rate is 5% and you decide to pay over a period of 5 years. What is your payment?
- For the cash flows shown in the table below, determine the future worth in year 8 at an interest rate of 6% per year. Year 2 3 4 5 6 Cash flow,$ 100,000 125,000 150,000 175,000 200,000
- What is the present value of $75 at the end of year 1, $225 at the end of year 2, and $300 at the end of year 4? There is no cash flow at the end of year 3. Use a discount rate of 6.25%. a. $411.57
- We are investing in a maintenance project that will increase annual revenues by $10,000 over ten years. What is the present value of those revenues, if the project is financed at 7% interest, compounded annually? What will the future worth of those reven
- A proposed investment will provide cash flows of $30,000, $9,000 and $6,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 14%, determines the present value of these cash flows at Year 2.
- A proposed investment will provide cash flows of $30,000, $9,000 and $6,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 14%, determines the present value of these cash flows at Year 1.
- A proposed investment will provide cash flows of $30,000, $9,000 and $6,000 at the end of Years 1, 2 and 3, respectively. Using a discount rate of 14%, determines the present value of these cash flows at Year 3.
- Consider a cash flow and interest profile as shown: The worth at the end of Year 3 of these cash flows is: $6, 792.52 $6, 540.00 $6, 100.00 $6, 302.68
- You own a contract that promises an annuity cash flow of $200 end-of-the-year cash flows for each of the next 4 years. (Note: The first cash flow is exactly 1 year from today). At an interest rate of 7%, what is the future value of this contract exactly 4
- Draw and solve the Cash Flow Diagram for Future Value "F_11". This is a 10 year Cash Flow, and interest rate is a compounded 9%, but l want the Future Value at Year 11. a. $5000.00 is Invested Today
- Draw and solve the Cash Flow Diagram for Future Value "F_11". This is a 10 year Cash Flow, and interest rate is a compounded 9%, but I want the Future Value at Year 11. a. $5000.00 is Invested Today
- A project has estimated annual net cash flows of $70,000 for four years and is estimated to cost $190,000. Assume a minimum acceptable rate of return of 10%. Determine (1) the net present value of t
- Consider the following cash flows: Year Cash Flow 2 $15,000 3 24,000 5 33,000 Assume an interest rate of 6.9 percent per year. Requirement 1: If today is Year 0, what is the future value of the cas
- For the cash flows shown, calculate the future worth in year 8 using i 10 per year Year 0 1 2 3 4 5 6 Cash Flow 100 100 100 100 100 300 300
- The following is the set of cash flow: A single $300 cash inflow at the end of year 5. Determine the present value of cash flows using a discount rate of 10%.
- Cost of investment is $200,000. Estimated cash flows are $50,000 per year for 3 years and then $500,000 per year for 3 years. Assume each cash flow is received evenly throughout the year. The specifie
- A Racism Awareness project has an initial cost of $5,000, with a yearly cost of $1,500, lasting indefinitely. The current interest rate is 3% per year. What is the capitalized cost of this project? a
- If the appropriate discount rate for the following cash flows is 9.75 percent per year, what is the present value of the cash flows? Year Cash Flow 1 CZK 2,800 2 0 3 8,100 4 1,940
- (TCO D) A bond currently sells for $887 even though it has a par of $1,000. It was issued two years ago and had a maturity of 10 years. The coupon rate is 7% and the interest payments are made semiannually. What is its YTM? (Show workings)
- (TCO D) A bond currently sells for $887 even though it has a par of $1,000. It was issued two years ago and had a maturity of 10 years. The coupon rate is 7% and the interest payments are made semiannually. What is its YTM?
- Consider an investment that pays $200 one year from now, with cash flows increasing by $200 per year through year 4. If the interest rate is 12%, what is the present value of this stream of cash flows
- Draw the cash flow diagram that represents following cash flows: $100 two years ago is equivalent to $144 now at 20% per year compound interest; find the equivalent three years in the future.
- What is the Present Value of a $2,000 inflow 2 years from now, and a $4,000 inflow 6 years from now and a $3,000 outflow 4 years from now. Assume an interest rate of 8% for years 1 and 2, 10% for year
- a) Bill invested $600 in an account paying 7.2% simple interest per year for 4 years. What will Bill's maturity value be at the end of 4 years? b) If Martin invests his money and earns 8.2% simple in
- Determine the value of "Y" from the cash flows given in the table below at an interest rate of 8%. Year 0 1 2 3 4 5 Cash flows -10,000 + Y 600 700 800 900 900
- You will be receiving cash flows of: $1,000 today, $2,000 at end of year 1, $4,000 at end of year 3, and $6,000 at end of year 5. What is the present value of these cash flows at an interest rate of 7%?
- A project has estimated annual net cash flows of $53,000 for nine years and is estimated to cost $317,437. Assume a minimum acceptable rate of return of 10%. Determine (1) the net present value of the
- A project has estimated annual net cash flows of $45,000 for five years and is estimated to cost $170,326. Assume a minimum acceptable rate of return of 12%. Determine (1) the net present value of the
- You are scheduled to receive $100,000 in three years. 8% is a fair rate. What is the present value of the future cash flow?
- Suppose you have just bought a 15-year, 8% semiannual coupon bond. Your purchasing price of the bond implies that the current YTM is 6%. Which of the following is true? a. Your purchasing price should have been lower than the par value. b. The cash flows
- A $10,000 bond is redeemable at par and bears interest at 10% compounded semi-annually. Find the purchase price ten years before maturity if the market rate compounded semi-annually is 10%.
- A $10,000 bond is redeemable at par and bears interest at 10% compounded semi-annually. Find the purchase price ten years before maturity if the market rate compounded semi-annually is 8%.
- A $10,000 bond is redeemable at par and bears interest at 10% compounded semi-annually. Find the purchase price ten years before maturity if the market rate compounded semi-annually is 12%.
- Consider an uneven cash flow stream: Year Cash Flow 0 3,000 1 2,000 2 1,500 3 0 4 2,000 5 4,000 a. What is the present (Year 0) value of the cash flow stream if the opportunity cost rate is 8 percent